Guide · Real Estate, Construction and Infrastructure
Infrastructure, P3 and Procurement
Infrastructure procurement in Canada combines contract law, trade agreements and long-term P3 structures, and now the federal Building Canada Act for national-interest projects. This guide explains procurement models, bidding law and bid challenges, P3 risk allocation and financing, trade-agreement rules and the Major Projects Office.
Key takeaways
- Formal tenders can create Contract A duties of fairness, as Tercon (2010 SCC 4) shows.
- Federal bid complaints to the CITT must be filed within 10 working days.
- P3 project agreements transfer design, construction, financing and maintenance risk to a project company.
- The Building Canada Act lets Ottawa list national-interest projects in Schedule 1 by order in council.
- The Major Projects Office, launched in August 2025, targets decisions within two years.
Infrastructure procurement in Canada at a glance
Infrastructure procurement in Canada brings together public procurement law, trade agreement obligations, contract structures such as public-private partnerships (P3s), and the federal and provincial approval regimes that apply to major projects. Governments, agencies and Crown corporations buy everything from consulting services to hospitals and transit lines, and the way they buy determines the legal rights of bidders and the risk that the winning consortium takes on. In 2026, the federal Major Projects Office and the Building Canada Act add a new layer for projects designated as being in the national interest.

This page explains the main procurement models, the law that governs bidding and bid disputes, P3 risk allocation and financing, trade-agreement rules, and the recent federal tools to accelerate nation-building projects. It is written for sponsors, contractors, lenders, operators and public owners.
| Element | Key rule or body | Source |
|---|---|---|
| Bidding obligations | Tender calls can create a "Contract A" with duties of fairness to compliant bidders | Tercon, 2010 SCC 4 |
| Federal bid challenges | Complaint to the Canadian International Trade Tribunal (CITT) within 10 working days of knowing the basis | CITT Act, s. 30.11; Procurement Inquiry Regulations |
| Federal infrastructure investment | Canada Infrastructure Bank invests in revenue-generating public-interest projects | Canada Infrastructure Bank Act, s. 6 |
| National-interest projects | Listing in Schedule 1 by order in council after notice and consultation | Building Canada Act (S.C. 2025, c. 2) |
| Federal coordination | Major Projects Office, launched 29 August 2025, target of decisions within two years | Prime Minister's Office release |
Procurement models and P3 structures
Canadian public owners use a spectrum of delivery models. Traditional design-bid-build and construction management remain common for smaller projects. Design-build transfers design and construction risk to one contractor. Alliance and progressive design-build models, increasingly used for complex transit and water projects, emphasize collaboration and shared risk. At the most integrated end, P3 models such as design-build-finance-maintain (DBFM) and design-build-finance-operate-maintain (DBFOM) transfer long-term performance risk to a private project company.
How a typical DBFM project works
In a DBFM project, a special-purpose project company signs a project agreement with the public owner. It subcontracts design and construction to a construction joint venture and long-term maintenance to a facilities management or operations partner. The project company raises private financing, usually a mix of equity from sponsors and long-term senior debt, which may be bank loans or bonds. During construction, the owner may make milestone or substantial completion payments; afterwards, it makes monthly availability payments over a long term, typically decades, reduced by deductions if the asset is unavailable or fails performance standards.
Provincial agencies such as Infrastructure Ontario and Partnerships British Columbia have developed standard project agreements and procurement processes for these models, and federal departments and Crown corporations use P3s for some assets. The standardization helps bidders, but each project agreement still contains project-specific risk allocation that must be reviewed carefully.
- Design and construction risk: passed to the construction joint venture through a back-to-back design-build contract.
- Operations and maintenance risk: passed to the service provider, with performance regimes and deductions.
- Financing risk: borne by the project company and its lenders, with owner protection on refinancing gains in some agreements.
- Retained owner risks: typically include certain site conditions, changes in scope, some changes in law and specified permits.
Bidding law and bid disputes
Infrastructure procurement in Canada is governed first by contract law. When an owner issues a formal call for tenders and a bidder submits a compliant bid, courts may find that a preliminary contract ("Contract A") is formed, which obliges the owner to treat bidders fairly and in accordance with the tender documents. In Tercon Contractors Ltd. v. British Columbia (Transportation and Highways), 2010 SCC 4, the Supreme Court found that a provincial ministry breached the tender process by accepting a bid from an ineligible party and that an exclusion clause did not shield it from liability.
Many complex procurements are structured as requests for proposals with negotiation, rather than formal tenders, specifically to avoid Contract A obligations. Whether Contract A arises depends on the documents and the parties' intentions. Owners should state clearly whether a process is intended to create contractual obligations, and bidders should read the process terms, including limitation of liability and "no claim" clauses, before investing heavily in a bid.
Federal bid challenges at the CITT
For federal procurements covered by trade agreements, potential suppliers can complain to the Canadian International Trade Tribunal under s. 30.11 of the Canadian International Trade Tribunal Act. The Procurement Inquiry Regulations require a complaint to be filed within 10 working days after the basis of the complaint became known or reasonably should have become known, or within 10 working days after the institution denies relief on a timely objection. The CITT can recommend remedies, including re-evaluation, re-tendering or compensation. The short deadline means bidders must act quickly when they suspect an error, often before they have all the facts.
Provincial and municipal procurements
Provincial and municipal procurements are challenged in the courts, usually through claims for breach of Contract A or of the duty of fairness, or sometimes through judicial review. Some provinces have bid dispute procedures in their procurement directives or trade agreement implementation. Debriefings offered by owners are a valuable source of information and should be requested promptly. Limitation periods for court claims are longer than the federal CITT deadline, but a bidder that waits may find that the contract has been signed and the work begun, which makes remedies other than damages unrealistic. Some procurement documents also require bidders to raise concerns during the process or lose the right to complain later.
Trade agreements and procurement rules
Trade agreements impose rules on covered public procurement above monetary thresholds, including non-discrimination, transparent processes, minimum bidding periods and bid challenge mechanisms. Domestically, the Canadian Free Trade Agreement (CFTA) covers federal, provincial and territorial governments and many municipal and broader public sector entities. Internationally, Canada's commitments under the World Trade Organization Agreement on Government Procurement, the Canada–European Union Comprehensive Economic and Trade Agreement (CETA), the Comprehensive and Progressive Agreement for Trans-Pacific Partnership (CPTPP) and other agreements open many Canadian procurements to foreign suppliers, including CETA's coverage of many sub-central entities.
Thresholds are adjusted periodically and differ by agreement and type of entity, so each procurement needs its own analysis. Exceptions apply for national security, some Indigenous procurement set-asides and certain sectors. Foreign bidders, including European and Asian contractors that often participate in Canadian transit P3s, rely on these agreements for access, while domestic bidders should understand which agreements apply so they can identify and challenge non-compliant processes.
When you receive procurement documents, immediately identify which trade agreements and which bid dispute process apply, and diarize the complaint deadline. At the federal level, ten working days can pass before a bidder has finished absorbing a debriefing, and a missed deadline usually ends the challenge.
Major projects and the Building Canada Act
The One Canadian Economy Act (Bill C-5, S.C. 2025, c. 2), which received royal assent on 26 June 2025, enacted the Building Canada Act. Under that Act, a project may be designated as being in the national interest by adding it to Schedule 1 by order in council, after publishing notice in the Canada Gazette for 30 days and consulting provinces and Indigenous peoples, and with provincial consent where the matter is within exclusive provincial jurisdiction.
Once a project is listed, federal authorities making decisions under listed federal statutes are to treat certain determinations as favourable, and the government issues a document setting out conditions. The designated minister must also cause an independent review of the status of each national interest project to be conducted every year. The Act has since been amended by Bill C-15.
The Major Projects Office, launched on 29 August 2025 and headquartered in Calgary, coordinates federal reviews for national-interest projects with the stated aim of making decisions within two years. In June 2026, the government began the process of listing the Mackenzie Valley Highway, the Grays Bay Road and Port and the Nuclear Waste Management Organization's deep geological repository, targeting decisions in the fall of 2026. Proponents should check the current Schedule 1 and the conditions documents rather than assume that a project has been listed.
What does not change
Listing does not remove the Crown's duty to consult Indigenous peoples, and it does not displace provincial permitting where provinces have jurisdiction. Projects still need environmental and technical approvals, community support and financing. For energy and resource projects, see our energy, mining and environment pages and our Indigenous law page.
Indigenous participation and community benefits
Infrastructure procurement increasingly asks bidders to show how a project will benefit Indigenous communities and local workers. Requirements may include Indigenous participation plans, subcontracting targets, training and employment commitments, and, on some projects, opportunities for Indigenous equity. Federal procurement policy sets a target for contracts awarded to Indigenous businesses, and some provinces and agencies apply their own community benefits frameworks. These commitments are usually scored in evaluation and then become contractual obligations, sometimes with financial consequences for shortfalls.
Bidders should treat these plans as core deliverables rather than marketing. Commitments must be realistic, supported by agreements with partners, and tracked through construction. For projects affecting Indigenous lands or rights, the Crown's consultation obligations run in parallel, and project companies often enter into separate agreements with affected communities. Our Indigenous equity and loan guarantees insight explains the financing tools.
Market sounding and unsolicited proposals
Before launching a major infrastructure procurement, owners usually conduct market sounding to test interest, risk allocation and timelines. Participating is worthwhile: it is often the best opportunity to influence the commercial terms before they are fixed. Some jurisdictions also accept unsolicited proposals, but the owner will typically still need to run a competitive process to comply with trade agreements and procurement policies, and the proponent's protections, such as reimbursement of costs or a right to match, should be agreed in writing.
Conflicts of interest and fairness monitors
Large public procurements commonly appoint a fairness monitor and impose strict rules on communications, conflicts of interest and the use of former public employees. Bidders that hire advisers who worked on the procurement for the owner, or that communicate outside the designated channels, risk disqualification. A compliance protocol for the bid team, including a log of contacts with the owner, is a simple and effective safeguard in infrastructure procurement.
Financing infrastructure procurement
P3 financing in Canada typically involves sponsor equity, often from infrastructure funds, pension plans and construction companies, and long-term senior debt raised through bank loans or private placement bonds. Lenders require a robust security package, direct agreements with the public owner giving them step-in rights, and protections against termination. The project agreement's compensation-on-termination provisions are central to bankability.
The Canada Infrastructure Bank, established under the Canada Infrastructure Bank Act, invests in revenue-generating infrastructure projects in the public interest and seeks to attract private and institutional investment. It has participated in transit, clean power, broadband, trade and transportation, and Indigenous infrastructure. Indigenous equity participation in infrastructure has also grown, supported by federal and provincial loan guarantee programmes. Our project and infrastructure finance page covers the financing side in more detail.
Change in law and inflation risk
Long-term infrastructure contracts must allocate the risk of changes in law, tariffs and inflation. Project agreements often distinguish between discriminatory changes in law, which the public owner bears, and general changes, which may be shared above a threshold. Construction price escalation since 2021, and tariffs since 2025, have pushed owners to revisit risk allocation, including through escalation mechanisms and progressive procurement models.
Disputes and contract management
Large infrastructure projects generate claims about delay, changes, site conditions and performance deductions. Project agreements usually provide a tiered dispute resolution process, often including an independent certifier, expert determination for technical issues, and arbitration or litigation. Ontario's Construction Act adjudication regime can also apply to disputes between contractors and subcontractors on public projects, and other provinces have similar regimes. Our construction and infrastructure disputes page explains how these cases are run.
Good contract management reduces disputes. Owners and project companies should keep contemporaneous records, follow notice requirements, and escalate issues early. Lenders monitor disputes closely because they affect cash flow and the risk of termination, and many credit agreements require lender consent before the project company settles a significant claim or agrees a material change to the project agreement. For public owners, transparent governance and early engagement with the project company help keep projects on schedule.
How TRW & Co helps
We advise public owners, sponsors, contractors, operators and lenders on infrastructure procurement and P3 projects in Canada. We help bidders review procurement documents and project agreements, form consortia and allocate risk among partners, prepare compliant bids and pursue or defend bid challenges. For owners, we help structure procurements that comply with trade agreements and are defensible in court. We also advise on major project approvals and Indigenous partnerships, and coordinate with counsel licensed in the relevant province where needed. See also our construction law and infrastructure and transportation pages. This page is general information, not legal advice. To discuss a procurement, contact us.
Frequently asked questions
What is Contract A in Canadian procurement law?
Contract A is a preliminary contract that may arise when an owner issues a formal call for tenders and a bidder submits a compliant bid. It obliges the owner to follow the tender terms and treat bidders fairly. Whether it arises depends on the procurement documents, and many complex procurements are designed to avoid it.
How do I challenge a federal procurement decision?
For federal procurements covered by trade agreements, a potential supplier can file a complaint with the Canadian International Trade Tribunal. Under the Procurement Inquiry Regulations, the complaint must be filed within 10 working days after the basis of the complaint became known or reasonably should have become known, or after an objection is denied.
Can foreign companies bid on Canadian infrastructure projects?
Yes. Many procurements are open to foreign suppliers, and trade agreements such as CETA, the CPTPP and the WTO Agreement on Government Procurement guarantee access for covered procurements above thresholds. Foreign bidders often participate in P3 consortia with Canadian partners, and must comply with security and local requirements.
What does listing under the Building Canada Act do?
A project listed in Schedule 1 is treated as being in the national interest, and federal decision-makers under specified statutes are to treat certain determinations as favourable, subject to conditions. Listing requires notice, consultation and, in exclusive provincial jurisdiction, provincial consent. It does not remove the duty to consult Indigenous peoples.
Who finances P3 projects in Canada?
Typically sponsors such as infrastructure funds, pension plans and construction companies provide equity, and banks or bond investors provide long-term senior debt. The Canada Infrastructure Bank may also invest in revenue-generating public-interest projects. Lenders rely on direct agreements with the public owner and compensation-on-termination provisions.
Sources
- Canadian International Trade Tribunal Act, s. 30.11
- Canadian International Trade Tribunal Procurement Inquiry Regulations (SOR/93-602)
- Canada Infrastructure Bank Act (S.C. 2017, c. 20, s. 403)
- One Canadian Economy Act (S.C. 2025, c. 2)
- Prime Minister launches the Major Projects Office (29 August 2025)
- Tercon Contractors Ltd. v. British Columbia (Transportation and Highways), 2010 SCC 4
General information only, not legal advice. References to statutes, courts and authorities describe published law and practice at the date shown.