National Interest Projects Under the Building Canada Act
National interest projects listed under the Building Canada Act receive a single federal conditions document in place of multiple separate approvals. This note explains how projects are designated, what the conditions document replaces, the Major Projects Office, Indigenous consultation and the legal challenge risks, with Pacific Link as the first listed project.

Key takeaways
- The Building Canada Act, Part 2 of Bill C-5, received royal assent on 26 June 2025.
- Listing requires 30 days' Gazette notice, provincial consultation and consent where provincial jurisdiction is exclusive.
- A single document under s. 7 is deemed to be each specified federal authorization, with conditions.
- The West Coast Oil Pipeline, now Pacific Link, was added to Schedule 1 on 1 October 2026.
- Consultation with affected Indigenous peoples is required before listing, before issuing the document and before amendments.
What national interest projects are
National interest projects are projects named in Schedule 1 of the Building Canada Act, enacted as Part 2 of the One Canadian Economy Act (Bill C-5, S.C. 2025, c. 2), which received royal assent on 26 June 2025. Once a project is listed, every determination, finding and opinion needed for the listed federal authorizations is deemed to be made in favour of the project (s. 6(1)), and the responsible Minister issues a single document that is deemed to be each specified federal authorization, with conditions (s. 7). The listing decision answers whether the project goes ahead federally; the conditions document decides how.

As of the Act's current consolidation, Schedule 1 contains one project: the West Coast Oil Pipeline, added by P.C. 2026-925 on 1 October 2026 and since renamed Pacific Link. This note explains how projects are designated, what the conditions document replaces, the role of the Major Projects Office, the Indigenous consultation requirements and the main legal challenge risks. It reflects the Act as consolidated on Justice Laws and government releases up to October 2026.
How national interest projects are designated
Under s. 5(1), the Governor in Council may, on the Minister's recommendation, add a project's name and detailed description, including its location, to Schedule 1 if it is of the opinion that the project is in the national interest. Several safeguards were added during the bill's passage:
- Notice and provincial role (s. 5(1.1)): a 30-day notice in the Canada Gazette, consultation with the province or territory, and its written consent if the project falls within areas of exclusive provincial or territorial jurisdiction.
- Factors (s. 5(6)): the extent to which the project can strengthen Canada's autonomy, resilience and security; provide economic or other benefits; have a high likelihood of successful execution; advance the interests of Indigenous peoples; and contribute to clean growth and climate objectives.
- Criteria order (s. 4.1): the Governor in Council may define "national interest" by order, which must set specific criteria that proponents must meet.
- Conflict of interest (s. 5(6.1)): the Minister must be satisfied that the proponent and its directors, officers and significant shareholders have not been found in violation of the Conflict of Interest Act, and that conflicted public office holders have recused themselves.
- Consultation (s. 5(7)): with other federal ministers, provinces and territories as appropriate, and Indigenous peoples whose s. 35 rights may be adversely affected.
- Time limits (s. 5(2)): no listing orders while Parliament is prorogued or dissolved, or after the fifth anniversary of the section coming into force.
Listing orders are exempt from the Statutory Instruments Act but must be published with reasons in the Canada Gazette, and project details must be posted in a public registry within 30 days (ss. 5(8)–(10), 5.1). A project can be delisted only before its conditions document is issued (s. 5(5)).
The conditions document
The core legal mechanism for national interest projects is the document under s. 7. It is deemed to be each authorization it specifies — for example, a Canada Energy Regulator certificate, a Fisheries Act authorization or a Species at Risk Act permit — and to meet all requirements of the enactments under which those authorizations are required (s. 7(3)). The enactments that can be covered are listed in Schedule 2, and s. 21(2) bars adding certain statutes, including the Investment Canada Act, the Canada Labour Code, the Criminal Code and the Indian Act.
| Element | Rule | Building Canada Act |
|---|---|---|
| Deemed favourable findings | Findings and opinions needed for authorizations are deemed made in favour of the project; an authorization cannot rest on that deeming alone | s. 6 |
| Proponent obligations | Proponent must still provide information, pay fees and take required measures | ss. 6(2), 7(2)(a) |
| Conditions | Must be conditions that could have been imposed under the underlying enactment | s. 7(5)–(6) |
| National security | Review of state-owned or foreign investments from hostile countries; Minister must be satisfied foreign investment risks are addressed | s. 7(2)(b.1), (d) |
| Transparency | Conditions, studies, departmental recommendations and reasons for rejecting them published at least 30 days before issuance | s. 8.1 |
| Expiry | Document expires if the project is not substantially started within five years | s. 7(10) |
| Amendment | Minister may amend conditions or add authorizations, after consultation | s. 8 |
Regulators keep a role. Before issuing a document for a project under the Canadian Energy Regulator Act, the Minister must consult the CER Commission and obtain its confirmation that the document will not compromise the safety or security of persons or regulated facilities (ss. 15, 17); the Nuclear Safety and Control Act has a parallel requirement involving the Canadian Nuclear Safety Commission (ss. 11, 13). Where a national interest project is also a designated project under the Impact Assessment Act, the planning phase provisions (ss. 9–17) do not apply and an impact assessment is deemed required (s. 19), so assessment work feeds into the conditions rather than determining whether the project proceeds.
Pacific Link: the first listing in practice
The first listing shows how the Act is being used. Schedule 1 describes the West Coast Oil Pipeline as an interprovincial pipeline "capable of transporting one million barrels per day" of Canadian crude from a receipt terminal at Bruderheim, Alberta to a deepwater port near Delta, British Columbia, with a pipeline of up to about 1,250 km, roughly 11 pump stations, power interconnection and a marine loading facility for very large crude carriers. The Gazette order identifies Trans Mountain Corporation, the Alberta Petroleum Marketing Commission and Pembina Pipeline Corporation as owners.
According to the government's October 2026 release, the conditions document is intended to serve as the CER certificate and to cover authorizations that would otherwise come from separate ministers, such as Fisheries Act authorizations and Species at Risk Act permits. The release also states that the route was chosen to avoid British Columbia's North Coast. The listing followed the Canada–Alberta arrangements of 2025 and 2026 under which Alberta committed to submit a pipeline proposal to the Major Projects Office.
For investors and lenders, the key point is that listing reduces approval risk but shifts attention to the content of conditions, provincial permits, Indigenous participation, cost and commercial support. Financing documents for national interest projects should treat issuance of the conditions document, the absence of successful challenges within limitation periods, and satisfaction of material conditions as separate milestones.
The Major Projects Office
Section 20 allows an office to be established to coordinate the exercise of powers under the Act and the listed enactments and to act as a point of contact for proponents. The government launched the Major Projects Office on 29 August 2025, headquartered in Calgary, with a stated target of approvals within two years (Prime Minister's release). For Pacific Link, the government said the Office, supported by the CER, will run the review and consultations and work to finalize conditions by 1 September 2027 (release of 1 October 2026).
The Office also handles projects that are not listed: proponents can seek coordination and single-window support for projects that proceed under the ordinary regulatory regimes. In June 2026 the government began the process to list the Mackenzie Valley Highway, the Grays Bay Road and Port and the Nuclear Waste Management Organization's deep geological repository (One Canadian Economy release); proponents should check the Canada Gazette and registry for the status of these listings.
Indigenous consultation for national interest projects
The Act embeds consultation at three points: before listing (s. 5(7)), before the conditions document is issued (s. 7(2)(c)), and before conditions are amended (s. 8(3)). For the conditions document, the Minister must ensure a process allowing the "active and meaningful participation" of affected Indigenous peoples, and publish a report of the consultation within 60 days after issuance (s. 7(2.1)). The preamble also refers to the rights in the United Nations Declaration on the Rights of Indigenous Peoples.
Because listing removes the question whether the project proceeds from the federal approval process, consultation focuses on routing, mitigation, accommodation and economic participation. Proponents should start engagement before nomination, document it carefully, and design ownership or benefit arrangements early. For Pacific Link, the government said Indigenous communities would be offered at least a 10% ownership interest supported by loan guarantee programs.
The constitutional duty to consult continues to apply independently of the statute. Its content depends on the strength of the claim and the seriousness of the potential impact, and the Crown may rely on regulatory processes to fulfil it if those processes are adequate. See our notes on impact benefit agreements and Indigenous equity ownership and loan guarantees.
Legal challenge risk for national interest projects
Designation narrows but does not eliminate litigation risk. The main avenues are:
- Judicial review of listing orders and conditions documents in the Federal Court, on grounds such as failure to follow the statutory steps (Gazette notice, provincial consent where required, consultation), unreasonableness or procedural unfairness.
- Inadequate Indigenous consultation or accommodation, which has historically been the most successful ground for quashing major project approvals in Canada.
- Constitutional challenges to the Act or its application, including division of powers arguments. The Supreme Court's opinion in Reference re Impact Assessment Act, 2023 SCC 23, shows that federal project-approval powers must stay anchored in federal heads of power; the provincial consent requirement in s. 5(1.1) responds to that concern.
- Provincial permits, which the Act does not replace. Projects still need provincial and municipal approvals, which can be challenged separately.
The Act's transparency requirements, including publication of departmental recommendations that were not accepted and the reasons (s. 8.1), will give challengers a detailed record. Conditions documents should therefore be built on a thorough evidentiary file, as if they were to be reviewed under the ordinary process.
What proponents should do
- Assess whether the project fits the s. 5(6) factors and any criteria order under s. 4.1, and whether a provincial consent is needed.
- Engage the Major Projects Office early and prepare the information each underlying authorization would require.
- Map provincial and municipal permits, which proceed in parallel.
- Build an Indigenous engagement and participation plan from the outset.
- Plan for foreign investment and national security review of investors.
- Prepare the record for judicial review from day one.
How TRW & Co helps
We advise proponents, investors, lenders and Indigenous partners on national interest projects and the wider federal approvals landscape. We assess eligibility and strategy for listing, map authorizations covered by the conditions document and those that remain provincial, help structure Indigenous equity and benefit arrangements, and review conditions for financing and investment purposes. Where litigation arises, we work with Canadian-licensed counsel on judicial review strategy. This work connects with our energy regulatory, Indigenous law and appellate and public law practices, and our note on pipeline approvals at the CER. To discuss a project, contact us.
Frequently asked questions
What does listing in Schedule 1 of the Building Canada Act do?
It deems every determination, finding and opinion needed for the specified federal authorizations to be made in favour of the project, and requires the Minister to issue a single document deemed to be those authorizations, with conditions that could have been imposed under the underlying statutes. The proponent must still provide information, pay fees and meet the conditions.
Which projects are national interest projects so far?
As of the Act's current consolidation, Schedule 1 lists one project: the West Coast Oil Pipeline from Bruderheim, Alberta to a port near Delta, British Columbia, added on 1 October 2026 by P.C. 2026-925 and now called Pacific Link. The government began the listing process for other projects in June 2026.
Does the Building Canada Act replace provincial approvals?
No. It covers federal authorizations under the statutes and regulations listed in Schedule 2. Provincial and municipal permits remain necessary, and a project within exclusive provincial jurisdiction cannot be listed without the province's written consent.
Can a listing or conditions document be challenged in court?
Yes. Orders and documents can be challenged by judicial review, for example for failure to follow statutory steps or inadequate consultation with Indigenous peoples, and constitutional challenges are possible. The Act's publication requirements will create a detailed record for any review.
Sources
- Building Canada Act, S.C. 2025, c. 2, s. 4 (Justice Laws)
- One Canadian Economy Act, S.C. 2025, c. 2 (annual statute)
- Prime Minister of Canada: West Coast Oil Pipeline listed, now known as Pacific Link (1 October 2026)
- Prime Minister of Canada: launch of the Major Projects Office (29 August 2025)
- Canada initiates process to list major projects under the Building Canada Act (June 2026)
General information only, not legal advice. References to statutes, courts and authorities describe published law and practice at the date shown.