Guide · Real Estate, Construction and Infrastructure
Construction Law
Construction law in Canada combines standard-form contracts, provincial lien and holdback statutes, and fast-moving prompt payment and adjudication rules. This guide explains contracting models and CCDC forms, Ontario's payment deadlines and the changes in force since 1 January 2026, liens and trusts, adjudication, insurance and bonding.
Key takeaways
- Ontario owners must pay proper invoices within 28 days unless they give notice of non-payment within 14 days.
- Since 1 January 2026, defective invoices are deemed proper unless the owner flags them within seven days.
- Owners must now release accrued holdback annually after each contract anniversary.
- Liens generally must be preserved within 60 days of the triggering event.
- Adjudicators decide within 30 days, and payment is due within 15 days of the determination.
Construction law in Canada: the essentials
Construction law in Canada rests on three pillars: the construction contract, usually based on a standard form; provincial lien and holdback legislation that protects those who supply services and materials; and, increasingly, prompt payment and adjudication statutes that keep money moving down the payment chain. Because construction and property are provincial matters, the rules differ across the country, and federal projects on federal land have their own prompt payment regime. Insurance and surety bonding complete the picture.

This page explains how those pillars fit together, using Ontario's Construction Act as the main example because it has the most developed prompt payment and adjudication system and was amended again with effect from 1 January 2026. It then points out where other provinces differ and what owners, contractors, lenders and subcontractors should do to protect themselves.
| Ontario rule | What it requires | Provision |
|---|---|---|
| Owner payment | Pay a proper invoice within 28 days of receipt | s. 6.4(1) |
| Notice of non-payment | Owner must give notice within 14 days to withhold a disputed amount | s. 6.4(2) |
| Deemed proper invoice | A defective invoice is deemed proper unless the owner flags the deficiency within seven days | s. 6.1(2), in force 1 January 2026 |
| Contractor to subcontractor | Pay within seven days of receiving payment | s. 6.5(1) |
| Basic holdback | 10% retained by each payer | s. 22(1) |
| Annual holdback release | Owner publishes notice and releases accrued holdback after each contract anniversary | s. 26(2), in force 1 January 2026 |
| Lien preservation | Generally within 60 days after the triggering event | s. 31 |
| Adjudication | Determination within 30 days of receiving documents; payment within 15 days | ss. 13.13, 13.19 |
Contracting models and CCDC forms
Canadian projects use a range of delivery models. In a traditional design-bid-build project, the owner retains a design team, then tenders a stipulated price contract. Construction management splits the builder's role into an advisory phase and a construction phase, either "for services" or "at risk". Design-build places design and construction under one contract, which simplifies the owner's interface but reduces control over design. Large public projects often use progressive design-build, alliance models or public-private partnerships.
The Canadian Construction Documents Committee (CCDC) publishes widely used standard forms, including stipulated price, cost-plus, construction management and design-build contracts, and subcontract forms. Owners rarely use them unchanged. Supplementary conditions typically shift risk for unforeseen site conditions, extend indemnities, tighten notice requirements for claims, and adjust the treatment of delay, change orders and warranties. Contractors should read the supplementary conditions as closely as the base form, because that is where most of the risk sits.
Tendering and the bidding contract
Where an owner calls for tenders, Canadian construction law may treat the call and each compliant bid as forming a preliminary contract (often called "Contract A") that obliges the owner to follow its own tender rules and to treat bidders fairly. In Tercon Contractors Ltd. v. British Columbia (Transportation and Highways), 2010 SCC 4, the Supreme Court held that a provincial ministry breached the tender process by accepting a bid from an ineligible bidder, and that the exclusion clause in the tender documents did not protect it. Owners should therefore draft tender documents carefully and follow them, and bidders should make sure their bids are compliant, because a non-compliant bid may not create any contractual rights at all.
Clauses that drive disputes
- Notice provisions: strict time limits for notifying claims for delay, changes and extra costs, which courts often enforce.
- Changes and change directives: who can order changes, how they are priced and what happens while price is disputed.
- Concealed or unknown conditions: who bears the risk of subsurface conditions that differ from reports.
- Delay and liquidated damages: schedules, float, extensions of time and caps on liability.
- Price escalation: whether material price increases, including those caused by tariffs, are recoverable.
- Termination and suspension: rights on default, for convenience and on non-payment.
Prompt payment under construction law
Prompt payment has transformed construction law in Ontario since 2019. Under s. 6.4(1) of the Construction Act, an owner must pay the amount payable under a proper invoice no later than 28 days after receiving it. An owner that disputes all or part of an invoice may refuse to pay only if it gives a notice of non-payment in the prescribed form within 14 days, specifying the amount and the reasons. Once paid, the contractor must pay its subcontractors within seven days, unless it has itself issued a timely notice of non-payment and undertakes to refer the dispute to adjudication.
What changed on 1 January 2026
Amendments made in 2024 (S.O. 2024, c. 20, Sched. 4), in force from 1 January 2026, strengthened the regime. An invoice that does not meet the formal requirements of a "proper invoice" is now deemed to be one unless, within seven days of receiving it, the owner tells the contractor in writing what is missing. That closes a tactic some owners used to delay the payment clock. The amendments also extended the time to start an adjudication to 90 days after the contract is completed, abandoned or terminated, unless the parties agree otherwise, and introduced mandatory annual release of holdback.
Other provinces and federal projects
Several other provinces have adopted prompt payment and adjudication regimes, including Alberta, with others at various stages. For construction work on federal real property, the federal Federal Prompt Payment for Construction Work Act provides a separate payment and adjudication framework. The details, such as payment periods, notice forms and adjudication bodies, differ, so contract administration processes need to be tailored to each jurisdiction.
Liens, holdbacks and trust obligations
Lien legislation gives contractors, subcontractors and suppliers a security interest in the owner's interest in the land, which they can enforce through a court-supervised sale if they are not paid. In Ontario, a lien must generally be preserved by registering a claim for lien on title, or giving written notice for public land, within 60 days after the relevant triggering event, such as publication of the certificate of substantial performance or completion, abandonment or termination of the contract. It must then be perfected by starting an action within the statutory period.
The holdback
Each payer must retain a 10% basic holdback under s. 22(1) until all liens that can be claimed against it have expired or been satisfied. Owners that release holdback early risk paying twice. From 1 January 2026, s. 26 requires owners to release accrued holdback annually: within 14 days after each anniversary of the contract, the owner publishes a notice of annual release of holdback specifying the amount it intends to pay and the payment date, and then pays at least 60 but not more than 74 days after the notice is published, subject to lien claims and other exceptions. Owners should build this into project cash flow, and contractors should track anniversaries.
Statutory trusts
Construction law also creates statutory trusts. Amounts received by an owner to finance the improvement, and amounts received by contractors and subcontractors on account of the contract price, are impressed with a trust in favour of those down the payment chain. Directors and officers who knowingly divert trust funds can be personally liable, and breach of trust claims often survive where lien rights have expired. Contractors should keep project accounts clear enough to show how funds were used.
Calendar three dates on every project: the 14-day window for a notice of non-payment, the seven-day window to flag a defective invoice, and the 60-day lien preservation period. Missing any of them can cost a party its leverage or its security, and the deadlines run whether or not negotiations are ongoing.
Substantial performance, deficiencies and warranties
Many statutory deadlines run from substantial performance, so the certificate or declaration of substantial performance is a key document. Owners should make sure the payment certifier applies the statutory test rather than a contractual definition, and contractors should publish the certificate promptly so that lien periods start to run. After substantial performance, deficiency lists, warranty periods and the release of the final holdback all need coordinated management. A clear close-out process reduces the risk of late lien claims and disputes about who must fix what.
Adjudication and dispute resolution
Adjudication is a fast, interim process for payment and related disputes. In Ontario, a party gives a notice of adjudication, an adjudicator is appointed from the roster administered by the authorized nominating authority, and the adjudicator must generally make a determination within 30 days after receiving the required documents under s. 13.13, subject to extension. A party required to pay must do so within 15 days after the determination is communicated (s. 13.19), subject to holdback requirements. The determination is binding on an interim basis until a court or arbitrator decides otherwise, or the parties agree, and it can be challenged only on limited grounds through judicial review.
Disputes that adjudication does not resolve go to court or to arbitration if the contract provides for it. Construction litigation in Canada typically involves lien actions, breach of contract claims for delay and disruption, claims on bonds and claims against design professionals. Expert evidence on scheduling and quantum is central. Our construction and infrastructure disputes page explains how these cases run.
Choosing a forum
Adjudication suits discrete, time-sensitive payment disputes. Arbitration is useful for complex technical disputes and confidentiality, and many large projects include a tiered process that starts with negotiation and a dispute review board. Courts remain necessary for lien enforcement and claims involving many parties. A well-drafted dispute clause sets out how these processes interact so that parties do not fight about where to fight.
Insurance and surety bonding
Construction projects in Canada typically require builder's risk (course of construction) insurance, commercial general liability insurance, professional liability insurance for designers and, for some projects, wrap-up liability policies covering all participants. The CCDC forms contain standard insurance requirements, which owners often increase. Contractors should check that their policies match the contract, including waivers of subrogation and additional insured requirements.
Surety bonds protect owners and the supply chain. A performance bond responds when the contractor defaults, allowing the surety to complete the work or pay the owner's increased costs up to the bond amount. A labour and material payment bond protects subcontractors and suppliers who are not paid. In Ontario, s. 85.1 of the Construction Act requires contractors on "public contracts" above a prescribed price, meaning contracts with the Crown, a municipality or a broader public sector organization, to furnish both a labour and material payment bond and a performance bond in prescribed forms and amounts. Private owners often require bonds by contract.
Insolvency on the project
When a contractor or subcontractor becomes insolvent, construction law and insolvency law interact. Statutory trust funds may be excluded from the insolvent party's estate if they can be traced, lien claimants keep their security against the owner's interest, and the surety may step in under the performance bond. Owners should stop paying an insolvent contractor until they have confirmed who is entitled to the funds, and should give the notices the bond requires without delay.
Claims on bonds
Bond claims require strict compliance with notice provisions and limitation periods in the bond wording. Claimants should read the bond as soon as payment problems emerge, give notice in the required form and keep records of the work supplied.
Construction law for owners, lenders and contractors
Different participants face different construction law risks. Owners need contract administration processes that meet prompt payment deadlines and holdback obligations, and clear authority over who can certify invoices and issue notices. Lenders financing construction need to manage the priority of their advances against lien claimants, require evidence that holdbacks are retained and released properly, and obtain step-in rights. Contractors need to manage their supply chain, pass through risk fairly, and keep the documentation that supports claims for delay and extra work.
Subcontractors and suppliers are protected by lien rights, trust provisions, payment bonds and prompt payment, but those protections depend on acting within deadlines. A supplier who waits too long to preserve a lien or to give notice under a bond can lose security even if its claim is valid.
Tariffs, escalation and supply risk
Tariffs and counter-tariffs on steel, aluminum and other materials have made price escalation a live issue in 2025 and 2026. Contracts signed on a fixed-price basis without escalation clauses leave the contractor exposed. Owners and contractors are increasingly negotiating escalation formulas tied to published indices, allowances for specified materials, or change-in-law clauses that cover tariffs. Our tariffs, CUSMA and customs page explains the trade measures in force.
How TRW & Co helps
We advise owners, developers, contractors, lenders and public bodies on construction law across Canada. Our work includes drafting and negotiating construction contracts and supplementary conditions, designing payment and holdback processes that comply with prompt payment rules, advising on lien, trust and bond claims, and managing disputes through adjudication, arbitration or litigation with counsel licensed in the relevant province. We also connect construction issues with P3 and procurement, project finance and commercial real estate. This page is general information, not legal advice. To discuss a project, contact us.
Frequently asked questions
What is a proper invoice under Ontario construction law?
It is an invoice that meets the requirements in s. 6.1 of the Construction Act, including information about the contractor, the work and the amount payable. Since 1 January 2026, an invoice that does not meet those requirements is deemed proper unless the owner identifies the deficiency in writing within seven days of receiving it.
How long does a contractor have to preserve a lien in Ontario?
Generally 60 days after the triggering event, such as publication of a certificate or declaration of substantial performance, or completion, abandonment or termination of the contract. The lien must then be perfected by commencing an action within the statutory period. The exact trigger depends on the claimant's position and the facts.
Is an adjudicator's decision final?
No. In Ontario, an adjudicator's determination is binding on an interim basis and must be paid within 15 days, but the parties can have the dispute finally decided by a court or arbitrator. Judicial review of the determination itself is available only on limited grounds.
Are surety bonds mandatory on Ontario public projects?
Yes, for public contracts above the prescribed price. Section 85.1 of the Construction Act requires contractors on contracts with the Crown, municipalities and broader public sector organizations to provide labour and material payment bonds and performance bonds in prescribed forms and amounts. Private owners often require bonds by contract.
Does the annual holdback release apply to all contracts?
The annual release requirement in s. 26 of the Ontario Construction Act came into force on 1 January 2026 and is subject to transition rules and exceptions, including for lien claims. Owners should check whether their contracts are covered and adjust payment processes and project budgets accordingly.
Sources
- Construction Act, R.S.O. 1990, c. C.30 (e-Laws consolidation from 1 January 2026)
- Federal Prompt Payment for Construction Work Act
- Tercon Contractors Ltd. v. British Columbia (Transportation and Highways), 2010 SCC 4
- Canada.ca: Canada's response to US tariffs, list of US products subject to counter-tariffs
General information only, not legal advice. References to statutes, courts and authorities describe published law and practice at the date shown.