Guide · Real Estate, Construction and Infrastructure

Municipal and Land Use Planning

Land use approvals decide what can be built in Canada and when, and the rules have changed quickly as provinces push for more housing. This guide explains official plans and zoning, appeal rights before the Ontario Land Tribunal, development charges and other levies, expropriation, and how to manage approval risk in transactions.

10 min read Updated
ENFR

Key takeaways

  • Planning is provincial law, delegated largely to municipalities through official plans and zoning by-laws.
  • Ontario zoning appeals must be filed within 20 days and are limited to defined parties who made submissions.
  • The Ontario Land Tribunal hears planning, development charge and expropriation compensation disputes.
  • Ontario development charge by-laws now expire 10 years after coming into force.
  • Expropriation compensation covers market value, disturbance, injurious affection and relocation difficulties.

How land use approvals work in Canada

Land use in Canada is controlled by the provinces and delegated in large part to municipalities. Each province has a planning statute that sets out how official plans (or municipal development plans), zoning by-laws, subdivisions and site plans are approved, who may appeal and to which tribunal. Municipalities then adopt plans and by-laws that apply to each parcel. Federal law rarely governs land use directly, although federal funding programmes, airports, ports, rail corridors and federal lands have their own rules, and Indigenous rights can affect decisions.

Land use planning in Canada: zoning map and development site under municipal review
Land use approvals in Canada: official plans, zoning, site plans, development charges and tribunal appeals.

For developers, investors and lenders, land use approvals are where value is created or lost. The questions are practical: what can be built as of right, which approvals are needed to do more, how long they will take, what they will cost in development charges and other levies, and who can appeal. This page uses Ontario as the main example because it has the most active development market and has changed its rules repeatedly since 2022, and then notes differences in other provinces.

Approval (Ontario)PurposeDecision-maker
Official plan amendmentChange the long-term land use designation or policiesMunicipal council (and, where applicable, an upper-tier or provincial approval authority)
Zoning by-law amendmentChange permitted uses, height, density and setbacks for a siteMunicipal council
Minor varianceSmall deviations from zoning standardsCommittee of adjustment
Plan of subdivision or condominiumCreate lots or condominium unitsApproval authority (often the municipality)
Site plan approvalBuilding location, access, landscaping and servicing detailsMunicipality (often delegated to staff)
Building permitCompliance with the Building Code and applicable lawChief building official

Official plans, zoning and site plans

The official plan sets out a municipality's long-term land use policies, including where growth, employment lands and natural heritage protection will go. Zoning by-laws implement the plan parcel by parcel. A proposal that conforms to the official plan but not to the zoning needs a zoning by-law amendment or minor variance; a proposal that conflicts with the official plan also needs an official plan amendment. Provincial policy statements and provincial plans, such as those covering the Greenbelt, set the overarching framework that municipal decisions must be consistent with or conform to.

Site plan control under s. 41 of Ontario's Planning Act deals with technical design matters such as building placement, access, parking, grading, servicing and landscaping. Recent amendments have narrowed site plan control for small residential projects and moved many site plan decisions to municipal staff to reduce delay. Holding provisions, interim control by-laws and temporary use by-laws are additional tools municipalities use to manage timing.

Inclusionary zoning and as-of-right permissions

Provinces have pushed municipalities to permit more housing as of right. In Ontario, amendments since 2022 permit additional residential units on many residential lots, and inclusionary zoning can require a share of affordable units in certain areas around major transit stations. British Columbia has introduced province-wide requirements for small-scale multi-unit housing and transit-oriented areas. These measures change the starting point for land use analysis: the question is often what the province now requires municipalities to permit, not only what the local by-law says.

Due diligence for development sites

  • Official plan designation and any secondary plan or site-specific policies.
  • Current zoning, including exceptions, holding provisions and prior variances.
  • Provincial plan areas, such as the Greenbelt or Oak Ridges Moraine, and conservation authority regulation limits.
  • Heritage designation or listing, and archaeological potential.
  • Servicing allocation, road widenings and agreements registered on title.
  • Development charges, parkland and community benefits charge exposure.

Land use appeals and the Ontario Land Tribunal

In Ontario, most land use appeals go to the Ontario Land Tribunal (OLT), created in 2021 when the Local Planning Appeal Tribunal, the Environmental Review Tribunal, the Board of Negotiation, the Conservation Review Board and the Mining and Lands Tribunal were amalgamated under the Ontario Land Tribunal Act, 2021. The OLT hears appeals of official plans, zoning by-laws, minor variances, subdivisions, development charges and expropriation compensation, among other matters.

Who may appeal has narrowed. Under s. 34(19) of the Planning Act, an appeal of a zoning by-law must be filed within 20 days after notice of the by-law is given, and may be brought by the applicant, a "specified person" (a defined list that includes utilities and certain pipeline and industrial operators), a public body or the registered owner of land to which the by-law would apply, in each case if they made submissions before the by-law was passed, and by the Minister. Many neighbours and residents' associations who used to appeal no longer have standing to do so on these matters.

Non-decision appeals

Applicants can also appeal if council fails to make a decision within the statutory period. Non-decision appeals give developers leverage when municipalities delay, but they move the matter into a litigation process with its own costs and timelines, and they can affect relationships with the municipality on future applications. Settlement through the OLT's mediation process is common, and settlements often include revised building envelopes, community contributions or phasing commitments.

Practical point

Appeal rights depend on having made submissions before the decision. Owners of land near a proposed development who may want to appeal should make oral submissions at the public meeting or written submissions to council before the by-law is passed, or they may lose standing entirely.

Development charges and other growth levies

Development charges fund growth-related capital costs such as roads, water, wastewater and transit. In Ontario, municipalities impose them through by-laws under the Development Charges Act, 1997, based on a background study. Since the More Homes Built Faster Act, 2022, a development charge by-law expires 10 years after it comes into force unless repealed earlier, and the Act includes exemptions and discounts for certain affordable, attainable and rental housing and for additional residential units. The province has continued to adjust the rules, including by changing what costs can be recovered and when charges are payable.

Alongside development charges, municipalities may require parkland dedication or cash in lieu under the Planning Act, and may impose a community benefits charge under s. 37 on higher-density development, capped as a percentage of land value. Developers should model all of these charges early, because they can materially change project returns.

Timing and freezes

For many developments, the development charge rate is frozen at the date of a complete site plan or zoning application for a period after approval, subject to interest, and payment may be deferred for some rental and institutional development. These rules reward early, complete applications, and they make the date of a complete application a value point that buyers of development land should verify from municipal records rather than assume. Agreements of purchase and sale for development land should allocate the risk of development charge increases and identify who bears charges that become payable before closing.

Development agreements and municipal securities

Approvals usually come with conditions. Subdivision, site plan and rezoning approvals often require the owner to enter into a development agreement with the municipality, registered on title, covering roads and services to be built, cost-sharing, conveyances of land, phasing and warranties. The municipality typically requires securities, often letters of credit, to guarantee completion of the works, released in stages as works are accepted. These agreements bind successors in title, so buyers of partly developed land inherit obligations they may not have negotiated.

Front-ending and cost-sharing agreements among landowners are also common in growth areas, where one developer pays for infrastructure that benefits others and recovers part of the cost later. Lenders and buyers should review these agreements carefully, because unpaid contributions or undelivered works can delay building permits for the whole area.

Conservation authorities and environmental constraints

In Ontario, conservation authorities regulate development in and near wetlands, floodplains, shorelines and hazardous lands through permits. Their role in reviewing planning applications was narrowed by provincial legislation in 2022 and 2024, but their permitting role continues. Other environmental constraints include provincially significant wetlands, species at risk habitat, source water protection areas and contaminated land, which may require a record of site condition before a change to a more sensitive use. Each can shape the developable area of a site, so constraint mapping is a standard early step.

Servicing capacity

Even with zoning in place, a development cannot proceed without water and wastewater capacity. Many municipalities allocate servicing capacity through council policies, and allocation can be withdrawn if a project does not proceed within set timeframes. Investors should confirm allocation status and any conditions, and should not assume that a zoned site is serviceable on the timetable they need.

Expropriation and compensation

Expropriation allows public authorities to take land for public purposes, such as transit, highways and utilities, subject to statutory procedures and compensation. In Ontario, the Expropriations Act requires an expropriating authority to compensate the owner, and s. 13(2) bases compensation on the market value of the land, damages attributable to disturbance, damages for injurious affection and any special difficulties in relocation. Where market value is based on a use other than the existing use, disturbance damages are generally not payable.

Owners can usually request a hearing of necessity before an inquiry officer for some expropriations, although recent provincial legislation has removed or limited that step for certain priority transit and infrastructure projects. Compensation disputes go to the OLT. Businesses located on land that will be expropriated should document their operations, relocation costs and losses carefully, and should understand that offers made by the authority can be accepted without prejudice to a claim for more in many cases.

Injurious affection without a taking

Owners whose land is not taken but is harmed by the construction of public works may also have a claim for injurious affection in limited circumstances. These claims are fact-specific and subject to strict time limits, so owners near major infrastructure projects should take advice early.

Municipal liability and judicial review

Outside the tribunal system, municipal decisions can sometimes be challenged by judicial review, for example where council acts outside its statutory powers, fails to follow required procedures or acts in bad faith. Courts generally defer to municipal decision-making, applying the reasonableness standard of review, and they do not substitute their own planning judgment. Claims for damages against municipalities for planning decisions face significant hurdles, so the statutory appeal route is usually the practical remedy. Where a by-law is challenged as illegal, timing and standing rules are strict, and an application should be brought promptly.

Land use rules in other provinces

Every province has its own planning statute and appeal structure. British Columbia's local governments act under the Local Government Act and, in Vancouver, the Vancouver Charter; the province has recently imposed housing targets and required zoning changes for small-scale multi-unit and transit-oriented housing. Alberta municipalities act under the Municipal Government Act, with subdivision and development appeal boards and the Land and Property Rights Tribunal. In Quebec, the Act respecting land use planning and development governs metropolitan and regional plans, municipal planning by-laws and approvals, often with referendum procedures for zoning changes.

The principles are similar across provinces: plans set policy, by-laws implement it, and approvals and appeals follow defined procedures with tight deadlines. But the details, especially about who may appeal and which tribunal decides, vary enough that national developers and lenders need province-specific advice for each project.

Federal involvement

Federal land use control is limited, but federal law matters for airports and their zoning regulations, ports, railways, fisheries and species at risk, and projects on federal lands. Federal housing programmes and infrastructure funding also influence municipal land use decisions through the conditions attached to funding.

Managing land use risk in transactions

Land use risk should be priced into every development transaction. Buyers can make their obligations conditional on obtaining approvals, but sellers often resist long conditional periods. Alternatives include staged deposits, price adjustments tied to approved density, and vendor take-back financing that shares the risk. Lenders need to understand how approval delays affect timelines and cost overruns, and joint venture agreements should address who leads the approvals process and how appeals are funded.

  • Confirm approvals already in place and whether they lapse if not acted on.
  • Review development agreements and conditions registered on title.
  • Check the status of any appeals, including third-party appeals of nearby approvals that may affect servicing or access.
  • Model development charges, parkland and community benefits charge exposure and any freezes.
  • Assess expropriation risk where the site is near planned transit or road corridors.

Planning law and real estate law intersect constantly. Our pages on commercial real estate, construction law and real estate and REITs cover the transactional side.

How TRW & Co helps

We help developers, investors, lenders and landowners understand and manage land use risk in Canada. That includes approvals due diligence for acquisitions, structuring purchase agreements and joint ventures around entitlement risk, analysing development charge and levy exposure, and advising on expropriation and compensation. Where a matter proceeds before a municipal council or a tribunal such as the Ontario Land Tribunal, we coordinate with planning consultants and with counsel licensed in the province. We also connect land use questions with real estate and infrastructure strategy more broadly. This page is general information, not legal advice. To discuss a site, contact us.

Frequently asked questions

Who can appeal a zoning by-law in Ontario?

Under s. 34(19) of the Planning Act, appeals may be brought within 20 days of notice by the applicant, a specified person, a public body or a registered owner of land to which the by-law applies, if they made submissions before it was passed, and by the Minister. Most other third parties no longer have standing.

What is the Ontario Land Tribunal?

It is an adjudicative tribunal created in 2021 by amalgamating several bodies, including the Local Planning Appeal Tribunal. It hears appeals on planning matters, development charges, expropriation compensation and other land-related disputes, and it offers mediation as well as hearings.

How are development charges calculated?

Municipalities adopt development charge by-laws supported by a background study of growth-related capital costs. Charges vary by municipality and type of development, and provincial law sets exemptions, discounts and timing rules, such as freezing rates at the date of a complete application for a period after approval.

What compensation is payable on expropriation in Ontario?

Section 13(2) of the Expropriations Act bases compensation on market value, disturbance damages, injurious affection and special difficulties in relocation. Disturbance damages are generally not payable where market value is based on a higher and better use than the existing use. Disputes go to the Ontario Land Tribunal.

Do land use rules differ across provinces?

Yes. Each province has its own planning statute, appeal body and procedures. British Columbia, Alberta and Quebec use different approval structures and appeal rights from Ontario, so developers working in more than one province need local analysis for each project.

Sources

  1. Planning Act, R.S.O. 1990, c. P.13 (e-Laws consolidation from 1 July 2026)
  2. Ontario Land Tribunal Act, 2021, S.O. 2021, c. 4, Sched. 6
  3. Development Charges Act, 1997, S.O. 1997, c. 27
  4. Expropriations Act, R.S.O. 1990, c. E.26

General information only, not legal advice. References to statutes, courts and authorities describe published law and practice at the date shown.