Construction Adjudication: Winning a Fast-Track Dispute

Construction adjudication lets contractors, subcontractors and owners resolve payment disputes in weeks, with determinations that bind until a court or arbitrator decides otherwise. Ontario, Alberta, Saskatchewan and the federal government have regimes; British Columbia does not yet have one in its lien statute.

Contractor and owner reviewing documents for construction adjudication of a payment dispute in Canada

Key takeaways

  • Ontario adjudication covers valuation, payment, change orders, set-off and holdback under O. Reg. 264/25.
  • Ontario referrals must start within 90 days after completion, abandonment or termination; Alberta's within 30 days of final payment.
  • Ontario adjudicators decide within 30 days of receiving documents; payment is due within 15 days.
  • Judicial review is narrow: leave within 35 days in Ontario, application within 30 days in Alberta.
  • The federal prompt payment and adjudication regime has applied to federal construction since 9 December 2023.

Construction adjudication in Canada: the short answer

Construction adjudication is a statutory, fast-track process for resolving payment and related disputes during and shortly after a construction project. An independent adjudicator decides the dispute within weeks, and the determination is binding on an interim basis: the parties must comply, but can later revisit the merits in court or arbitration. Ontario, Alberta and Saskatchewan have provincial regimes, and the federal Federal Prompt Payment for Construction Work Act, in force since 9 December 2023, applies adjudication to construction on federal real property. British Columbia's Builders Lien Act, as consolidated to 10 November 2026, contains no prompt payment or adjudication provisions.

Contractor and owner reviewing documents for construction adjudication of a payment dispute in Canada
Construction adjudication turns payment disputes into decisions within weeks rather than years.

For contractors and subcontractors, adjudication is a powerful cash-flow tool. For owners, it means disputes about invoices, change orders and holdback can produce enforceable payment obligations quickly. This article compares the regimes, explains what can be referred, the timelines, selection of adjudicators, evidence and determinations, enforcement and judicial review, and how to prepare. It is general information, not legal advice.

What disputes can be referred to construction adjudication

In Ontario, s. 13.5 of the Construction Act allows a party to a contract or subcontract to refer a dispute with the other party respecting any prescribed matter, or any matter they agree to. Since 1 January 2026, s. 19 of O. Reg. 264/25 prescribes:

  • the valuation of services or materials provided under the contract;
  • payment under the contract, including for approved or unapproved change orders and proposed change orders;
  • disputes that are the subject of a notice of non-payment;
  • amounts retained as trust or lien set-off;
  • payment of holdback under s. 26; and
  • where reasonably necessary to decide one of those matters, the scope of work, requests for a change in price and requests for extensions of time.

In Alberta, s. 33.4 of the Prompt Payment and Construction Lien Act (PPCLA) allows parties to a contract or subcontract to refer disputes respecting prescribed matters, under the regulations or the procedures of the relevant Nominating Authority. Saskatchewan's Builders' Lien Act contains a similar framework for prescribed matters. On federal projects, the federal Act provides adjudication of payment disputes between parties in the contracting chain. In each regime, an adjudication generally addresses a single dispute unless the parties agree otherwise.

Timelines: how fast is construction adjudication?

Speed is the defining feature. The key deadlines differ by jurisdiction:

IssueOntarioAlberta
Latest time to startNo more than 90 days after the contract is completed, abandoned or terminated (subcontracts: earliest of listed dates), unless agreed otherwise (s. 13.5(3)-(3.1))No more than 30 days after the date of final payment, unless agreed otherwise (s. 33.4(2))
Time for determination30 days after the adjudicator receives the documents, extendable by consent (s. 13.13)Set by regulation and Nominating Authority procedures
Payment of amount determinedWithin 15 days after the determination is communicated (s. 13.19(2))Order may be registered as a court order after 30 days, subject to conditions (s. 33.61)
Judicial reviewOnly with leave of the Divisional Court; motion within 35 days (s. 13.18)Application filed and served within 30 days of the notice of determination (s. 33.7)
Effect pending court or arbitrationBinding until a court, arbitrator or written agreement decides otherwise (s. 13.15)Binding unless the court directs otherwise, an arbitral award is made or the parties agree (s. 33.6(5))

Because the referring party controls the timing, it can prepare for months before serving notice, while the responding party may have only days to respond. Owners and contractors should therefore keep project records organized so they can respond quickly to a notice of adjudication.

Adjudicator selection

In Ontario, adjudications are administered through an Authorized Nominating Authority designated under the Act. The parties can agree on a registry adjudicator from the Authority's roster, or on a private adjudicator under a written agreement disclosing the terms and a fee of at least CAD 1,000 per hour (O. Reg. 264/25, s. 21). If agreement is unlikely, the referring party must ask the Authority to appoint a registry adjudicator. In Alberta, Nominating Authorities designated under the PPCLA appoint adjudicators and set procedures. Choosing an adjudicator with the right expertise (engineering, quantity surveying or legal) can matter as much as the merits, particularly for valuation and delay disputes.

Practical point

Prepare the referral package before serving notice: the contract documents, invoices, change orders, correspondence, schedules and a clear calculation of the amount claimed. Adjudicators decide quickly on the documents, and a well-organized record often decides the outcome.

Evidence, procedure and determinations

Construction adjudication is document-driven. In Ontario, the referring party delivers its documents to the adjudicator and the other party, the respondent replies within a short period, and the adjudicator has broad powers under s. 13.12 of the Construction Act and s. 29 of O. Reg. 264/25 to set procedure, request further documents, and draw on their own expertise. Oral hearings are uncommon and short. Determinations are written, and the adjudicator must send an electronic copy and then a certified copy to the parties. Ontario's Authority must publish determinations, with anonymization on request, for adjudications commenced on or after the first anniversary of O. Reg. 264/25.

The adjudicator may refuse to hear frivolous or vexatious disputes in Alberta (s. 33.6(3)), and may refer matters to court where it lacks jurisdiction or the court is more appropriate (s. 33.6(2)). In Ontario, a registry adjudicator's fee is either agreed with the parties or determined under s. 13.10(2) of the Construction Act and the Authority's fee schedule.

Enforcement and judicial review

A determination is only useful if it can be enforced. In Ontario, a party may file a certified copy of the determination with the court under s. 13.20, after which it is enforceable as a court order.

Interest accrues on late payments, and under s. 13.19(5) a contractor or subcontractor that is not paid an amount due under a determination may suspend further work until the amount, interest and reasonable suspension costs are paid. In Alberta, the clerk of the court registers an adjudicator's order as a court order if the conditions in s. 33.61 are met, including that at least 30 days have passed and no court order, arbitration or agreement has displaced it.

Judicial review is narrow. In Ontario, it requires leave of the Divisional Court, sought within 35 days, and the grounds are limited by the statute. In Alberta, an application must be filed and served within 30 days and does not stay the determination unless the court orders otherwise. Parties dissatisfied with a determination on the merits usually pay and pursue the underlying dispute in arbitration or litigation, where the matter is heard afresh.

Illustration: a mechanical subcontractor on an Ontario hospital project disputes the contractor's valuation of a change order worth CAD 400,000. It serves a notice of adjudication, and the adjudicator determines within 30 days of receiving the documents that CAD 310,000 is payable. The contractor must pay within 15 days, subject to holdback, and may later pursue its position in arbitration. The figures are hypothetical.

Federal projects and Saskatchewan

On construction projects for federal real property or federal immovables, the federal Act sets its own rules. Under s. 16, a contractor or subcontractor that has not been fully paid within the statutory or contractual time limit may obtain a determination from an adjudicator on the non-payment dispute. The notice of adjudication must be given no later than the 21st day after the later of the contractor's receipt of a certificate of completion and the expiry of the payment period for work covered by the last proper invoice.

The notice must also name a proposed adjudicator selected from the list maintained by the federal Adjudicator Authority; that choice cannot be restricted by contract. Under s. 18(2), the determination binds the parties unless they agree otherwise in writing or it is set aside by a court order or arbitral award. Contractors working for federal departments, or for service providers managing federal property, should check whether the federal Act rather than the provincial regime applies.

Saskatchewan's Builders' Lien Act also includes prompt payment and adjudication provisions. We have not reproduced its details here; timelines and procedures differ from Ontario's, so parties should consult the Saskatchewan legislation and regulations for each project.

Construction adjudication versus arbitration and litigation

Construction adjudication does not replace other dispute resolution; it sits in front of it. Arbitration and litigation remain the forums for final decisions on complex delay claims, defects, termination and large accounts. The list below highlights the differences parties weigh when choosing a route.

  • Speed: adjudication takes weeks; arbitration and litigation typically take many months or years.
  • Finality: adjudication is interim and can be revisited; arbitral awards and judgments are final subject to limited appeals.
  • Cost: adjudication is usually cheaper, but compressed timelines concentrate costs at the start.
  • Scope: adjudication is limited to prescribed or agreed matters; arbitration and courts can address all claims, including damages and declarations.
  • Confidentiality: Ontario will publish determinations for adjudications commenced on or after the first anniversary of O. Reg. 264/25, subject to anonymization requests; arbitration is usually private.

Common mistakes

  1. Missing the start deadline because the project's completion or termination date was not tracked.
  2. Referring an overly broad dispute that falls outside prescribed matters, inviting a jurisdictional objection.
  3. Failing to deliver complete documents with the referral, leaving the adjudicator to decide on an incomplete record.
  4. Ignoring the respondent's tight reply window, which can leave key evidence out of the record.
  5. Not paying a determination on time, triggering interest, suspension rights and enforcement steps.

Strategy for owners, contractors and subcontractors

  • Know the regime. Check which statute governs the project (province, federal property, or a P3 structure) and the applicable regulation.
  • Use notices properly. In Ontario, disputes about proper invoices depend on timely notices of non-payment, and failures can make amounts payable regardless of merits.
  • Plan the dispute portfolio. Decide which claims suit construction adjudication (valuation, payment, change orders) and which need full arbitration or litigation (complex delay, defects, termination).
  • Coordinate with liens and holdback. Adjudication does not replace lien rights; preserve liens on time while adjudication proceeds.
  • Draft contracts accordingly. Contracts can add agreed matters, choose procedures where the statute allows, and coordinate adjudication with arbitration clauses.

Related insights cover the 2026 Ontario Construction Act amendments and price escalation and delay claims.

How TRW & Co helps with construction adjudication

We advise owners, contractors, subcontractors and lenders on construction adjudication in Canada: assessing which regime applies, preparing and responding to referrals, selecting adjudicators, coordinating adjudication with lien, arbitration and litigation strategy, and enforcing or challenging determinations. Court steps are taken with counsel licensed in the relevant province. See our construction and infrastructure disputes and construction law pages, or contact us.

Frequently asked questions

What is construction adjudication?

A statutory process in which an independent adjudicator quickly decides construction payment and related disputes. The determination is binding on an interim basis: the parties must comply, but a court, arbitrator or written agreement can later decide the matter differently.

Which provinces have construction adjudication?

Ontario, Alberta and Saskatchewan have provincial regimes, and the Federal Prompt Payment for Construction Work Act applies to construction on federal real property. British Columbia's Builders Lien Act, as consolidated to 10 November 2026, does not contain adjudication provisions.

How long does construction adjudication take in Ontario?

The adjudicator must make a determination within 30 days after receiving the required documents, unless extended by consent. Amounts determined must be paid within 15 days after the determination is communicated, subject to holdback.

When is it too late to start an adjudication?

In Ontario, generally more than 90 days after the contract is completed, abandoned or terminated, with parallel subcontract rules, unless the parties agree otherwise. In Alberta, more than 30 days after the date of final payment under the contract or subcontract, unless the parties agree.

Can an adjudication determination be challenged?

Only narrowly by judicial review: in Ontario with leave of the Divisional Court sought within 35 days, and in Alberta by application within 30 days. More commonly, the losing party pays and pursues the merits in arbitration or litigation.

Sources

  1. Construction Act, R.S.O. 1990, c. C.30
  2. O. Reg. 264/25: Adjudications under Part II.1
  3. Prompt Payment and Construction Lien Act, RSA 2000, c. P-26.4
  4. Builders Lien Act, S.B.C. 1997, c. 45
  5. Federal Prompt Payment for Construction Work Act, S.C. 2019, c. 29, s. 387

General information only, not legal advice. References to statutes, courts and authorities describe published law and practice at the date shown.