Ontario Construction Act: 2026 Amendments Explained
The Ontario Construction Act changed on 1 January 2026. Owners must now release holdback annually, invoices are deemed proper unless flagged within seven days, adjudication has a new regulation and a post-completion window, and termination notices fix when lien periods start.

Key takeaways
- Owners must publish an annual holdback release notice within 14 days after each contract anniversary.
- Accrued holdback must be paid 60 to 74 days after the notice unless a lien is preserved.
- Invoices are deemed proper unless the owner flags deficiencies in writing within 7 days.
- O. Reg. 264/25 replaced O. Reg. 306/18 and lists adjudicable matters, including change orders and holdback.
- Notices of termination must be published within 7 days and fix the lien expiry start date.
Ontario Construction Act amendments: the short answer
On 1 January 2026, significant amendments to the Ontario Construction Act came into force, made by Schedule 4 to the Building Ontario For You Act (Budget Measures), 2024 and Schedule 2 to the Fighting Delays, Building Faster Act, 2025. The main changes are mandatory annual release of holdback, a deemed proper invoice rule, a new adjudication framework under O. Reg. 264/25 with a broader list of adjudicable matters and a post-completion window, longer deadlines for paying determinations and seeking judicial review, and a notice-of-termination rule that fixes when lien periods start after a contract ends. Owners, contractors, subcontractors and lenders all need to update contracts and payment processes.

Because most projects last more than a year, almost every active project in the province is affected. This article explains what changed, how the transition rules apply to contracts signed before 2026, and practical steps for each participant. It reflects the Act as consolidated from 1 January 2026 and is general information, not legal advice.
Mandatory annual release of holdback
Owners must still retain a 10% holdback under Part IV of the Ontario Construction Act, but the rules on releasing it changed. Under the re-enacted s. 26, following each anniversary of the date the contract was entered into, the owner must:
- publish, no later than 14 days after the anniversary, a notice of annual release of holdback in the prescribed form, stating the amount it intends to pay and the payment date; and
- at least 60 days but not later than 74 days after publishing the notice, pay the contractor all holdback accrued for services or materials supplied during the preceding year, unless a lien has been preserved or perfected and has not been discharged, vacated or satisfied.
The contractor must pay its subcontractors their accrued holdback within 14 days after receiving it, and the same cascade applies down the chain. If a lien prevented payment, holdback must be paid within 14 days after the circumstances preventing payment cease to apply. The former provisions on phased and annual release by agreement (ss. 26.1 and 26.2) were repealed.
For contracts entered into before 1 January 2026, s. 87.4(4) modifies the rule: the first anniversary to which s. 26 applies is the second contract anniversary falling after s. 26 came into force, and the first annual payment includes all holdback accrued before that date. Certain prescribed public-private partnership project agreements continue under the former s. 26.
| Change | Rule from 1 January 2026 | Provision |
|---|---|---|
| Annual holdback release | Notice within 14 days after each contract anniversary; payment 60 to 74 days after notice, subject to preserved liens | s. 26 |
| Holdback down the chain | Contractor pays subcontractors within 14 days after receipt | s. 26(5)-(6) |
| Deemed proper invoice | Invoice deemed proper unless owner gives written notice of deficiency within 7 days | s. 6.1(2) |
| Adjudication scope | Prescribed matters, including valuation, payment, change orders and holdback, plus agreed matters | s. 13.5; O. Reg. 264/25, s. 19 |
| Adjudication window | Notice within 90 days after completion, abandonment or termination | s. 13.5(3)-(3.1) |
| Paying a determination | Within 15 days after it is communicated | s. 13.19(2) |
| Judicial review leave motion | Within 35 days after the determination | s. 13.18(2) |
| Notice of termination | Publish within 7 days; publication date fixes termination date for lien expiry | s. 31(6)-(7) |
Prompt payment and the deemed proper invoice
Prompt payment timelines remain: an owner must pay a proper invoice within 28 days of receipt unless it gives a notice of non-payment within 14 days (s. 6.4), and contractors must pay subcontractors within set periods after that. The amendments add a deeming rule. Under s. 6.1(2), an invoice that contains the information required by the definition of "proper invoice" is deemed to be a proper invoice unless, no later than seven days after receiving it, the owner notifies the contractor in writing of the deficiency and what is needed to address it. The definition now also allows owners to request information reasonably necessary for their accounts payable systems.
The practical effect is to stop owners from sitting on invoices and later rejecting them for technical defects. Owners, particularly those with central accounts payable teams or external payment certifiers, need processes to review invoices within a week; contractors should ensure invoices contain every required element and keep proof of delivery. Under the amended rules on revisions, a contractor may revise a proper invoice with the owner's advance agreement, without changing its date.
Owners and their payment certifiers should calendar three deadlines for every invoice: 7 days to flag deficiencies, 14 days to deliver any notice of non-payment, and 28 days to pay. Missing the first can make an otherwise deficient invoice a proper invoice that starts the payment clock.
Adjudication under the amended Ontario Construction Act
Adjudication remains the fast-track interim dispute process, but its framework changed. The former regulation, O. Reg. 306/18, was revoked on 1 January 2026 and replaced by O. Reg. 264/25. Key points:
- Scope: under s. 13.5(1), a party may refer a dispute respecting any prescribed matter, or any matter the parties agree to. Section 19 of O. Reg. 264/25 prescribes valuation of services or materials; payment, including for approved or unapproved change orders and proposed change orders; disputes subject to a notice of non-payment; trust and lien set-off amounts; payment of holdback under s. 26; and, where reasonably necessary to decide another adjudicable matter, scope of work, requests for price changes and extensions of time.
- Timing: notices of adjudication must generally be given no more than 90 days after the contract is completed, abandoned or terminated, with a parallel rule for subcontracts, unless the parties agree otherwise.
- Consolidation: a party may require consolidation of related adjudications with the adjudicators' agreement and in accordance with the regulation.
- Private adjudicators: parties may agree to a private adjudicator under a written agreement disclosing terms and a fee of at least CAD 1,000 per hour.
- Payment and review: amounts determined must be paid within 15 days, and leave to seek judicial review must be sought from the Divisional Court within 35 days.
- Publication: the Authority must publish determinations, with anonymization on request, for adjudications commenced on or after the first anniversary of the regulation.
Our insight on construction adjudication across Canada explains the process in more detail.
Lien preservation and termination notices
Lien periods remain 60 days, running from the earlier of publication of a certificate or declaration of substantial performance and the date the contract is completed, abandoned or terminated (s. 31).
Because termination dates are often disputed, s. 31(6) now requires the owner, the contractor or another person whose lien may expire to publish a notice of termination in the prescribed form no later than seven days after a contract is terminated. Under s. 31(7), the date the first notice is published is treated as the termination date for lien expiry purposes. Subcontractors on terminated projects should watch for these notices, and owners terminating a contractor should publish promptly to start the lien clock. Transition rules preserve the earlier versions of s. 31(6) and (7) for termination notices published before the change.
Contract drafting after the Ontario Construction Act amendments
Standard contracts and supplementary conditions written for the pre-2026 regime need review. Clauses that tied holdback release only to substantial performance, or that allowed phased release by agreement under the repealed ss. 26.1 and 26.2, should be updated to reflect the mandatory annual cycle. Invoice provisions should list the information the owner reasonably needs for its accounts payable system, since the statutory definition now accommodates that, while avoiding conditions that make giving a proper invoice depend on prior certification, which s. 6.3(2) still prohibits.
Dispute resolution clauses should address the new adjudication framework: which additional matters, if any, the parties agree to refer, whether they prefer a registry or private adjudicator, how consolidation will work on multi-party projects, and how adjudication interacts with arbitration or litigation. Termination clauses should allocate responsibility for publishing the statutory notice of termination. Lenders' construction loan agreements should be aligned so that draws can fund annual holdback releases and the lender receives copies of notices and evidence of payment.
Enforcing adjudication determinations
Under s. 13.15(1), determinations remain binding on the parties until a court or an arbitrator under the Arbitration Act, 1991 decides the matter, or the parties agree otherwise in writing. Under s. 13.20 of the Ontario Construction Act, a party may file a certified copy of a determination with the court, after which it is enforceable as a court order; filing must occur by the later of the second anniversary of the determination and, if a leave motion for judicial review was brought, the second anniversary of its dismissal or final disposition. Interest accrues on late payments at the prejudgment interest rate. Under s. 13.19(1), payment obligations remain subject to holdback requirements.
Practical steps for owners, contractors and lenders
- Owners: diarize contract anniversaries, build annual holdback release into cash flow and loan draws, and update invoice review processes for the seven-day deeming rule.
- Contractors: update subcontracts to flow through annual holdback release, check invoices against the statutory definition, and track the 90-day adjudication window after completion or termination.
- Subcontractors and suppliers: monitor annual release notices and termination notices, which affect when holdback is paid and when liens expire.
- Lenders: revise construction loan agreements so that draw schedules fund annual holdback release and require evidence of compliance.
- Everyone: review standard forms and supplementary conditions, including CCDC documents, for consistency with the amended Act; see our insight on CCDC contracts.
Illustration: an owner and contractor sign a three-year contract on 1 March 2026. On 1 March 2027, the owner must publish a notice of annual release by 15 March 2027 and pay accrued first-year holdback between 60 and 74 days after publication, unless a lien has been preserved. Under the transition rule, a similar contract signed on 1 March 2025 would see its first mandatory release after the second anniversary falling after 1 January 2026, on 1 March 2027, including all holdback accrued since 2025.
How TRW & Co helps with the Ontario Construction Act
We advise owners, developers, contractors and lenders on the 2026 amendments to the Ontario Construction Act: updating contracts, subcontracts and loan agreements, designing holdback release and invoice processes, and advising on adjudication strategy and lien preservation. Proceedings in Ontario courts and before adjudicators are conducted with Ontario-licensed counsel, with whom we work. See our construction law and construction and infrastructure disputes pages, or contact us.
Frequently asked questions
When did the 2026 Ontario Construction Act amendments take effect?
The amendments made by Schedule 4 to the Building Ontario For You Act (Budget Measures), 2024 and Schedule 2 to the Fighting Delays, Building Faster Act, 2025 came into force on 1 January 2026. Transition rules in s. 87.4 modify their application to some existing contracts.
How does mandatory annual holdback release work?
After each anniversary of the contract date, the owner must publish a notice of annual release within 14 days and pay accrued holdback for the prior year 60 to 74 days after publication, unless a lien has been preserved or perfected and not resolved. Contractors pay subcontractors within 14 days of receipt.
What is a deemed proper invoice?
Under s. 6.1(2), an invoice containing the statutory information is deemed to be a proper invoice unless the owner notifies the contractor in writing of the deficiency within seven days of receiving it. This starts the 28-day payment period.
What can be adjudicated under the new regulation?
Section 19 of O. Reg. 264/25 prescribes valuation, payment including change orders, disputes subject to a notice of non-payment, set-off amounts and holdback payment, and, where necessary for those matters, scope of work, price changes and extensions of time. Parties may also agree to adjudicate other matters.
How do the amendments affect lien deadlines after termination?
Under s. 31(6) and (7), a notice of termination must be published within seven days after a contract is terminated, and the date the first notice is published is treated as the termination date for calculating the 60-day lien period.
Sources
General information only, not legal advice. References to statutes, courts and authorities describe published law and practice at the date shown.