Construction Lending, Holdbacks and Lien Priority in Canada
Construction lending exposes lenders to lien claimants who can rank ahead of the mortgage. Under s. 78 of Ontario's Construction Act, a building mortgage is subordinate to liens to the extent of any holdback deficiency. This note explains the priority rules, the 2026 annual holdback release regime and the loan protections that manage the risk.

Key takeaways
- A building mortgage ranks behind liens to the extent of any holdback deficiency under s. 78(2).
- Advances lose priority once a lien is preserved or the lender receives written notice of a lien.
- Owners must retain a 10% holdback on services and materials supplied.
- Ontario's mandatory annual holdback release applies from 1 January 2026.
- Cost-to-complete tests, title sub-searches and holdback accounts protect each advance.
Why lien priority matters in construction lending
Construction lending carries a risk that ordinary mortgage lending does not: the people who build the project can claim a lien that ranks ahead of the lender. Provincial construction lien statutes give contractors, subcontractors, suppliers and workers a lien on the owner's interest in the land for the value of their work. In Ontario, s. 78 of the Construction Act sets out how those liens rank against mortgages, and its central rule is blunt: a "building mortgage", meaning a mortgage taken to finance the improvement, is subordinate to the liens to the extent the owner failed to retain the statutory holdbacks, no matter when the mortgage was registered. A lender that funds a project without policing holdbacks can lose priority on the very advances it made.

This note focuses on Ontario, which has the most active lending market and the most recent amendments, and flags how other provinces differ. It covers the s. 78 priority scheme, the holdback and trust rules that lenders depend on, how to structure advances and cost-to-complete tests, and the protections that belong in every construction loan agreement.
The section 78 priority scheme in Ontario
Section 78 starts by giving liens priority over all conveyances, mortgages and other agreements affecting the owner's interest (s. 78(1)), then carves out the lender's position in several steps:
- Building mortgages (s. 78(2)). Where a mortgagee takes a mortgage intending to secure financing of an improvement, liens arising from that improvement rank ahead of the mortgage, and any mortgage taken out to repay it, to the extent of any deficiency in the holdbacks the owner was required to retain.
- Prior mortgages and prior advances (s. 78(3)). Mortgages registered before the first lien arose rank ahead of the liens to the extent of the lesser of the actual value of the premises when the first lien arose and the amounts advanced before then.
- Prior mortgages and later advances (s. 78(4)). Advances made after the first lien arose under a prior mortgage keep priority unless, at the time of the advance, a lien had been preserved or perfected, or the lender had received written notice of a lien.
- Subsequent mortgages (ss. 78(5)–(6)). Mortgages registered after the first lien arose rank behind liens to the extent of any holdback deficiency, and otherwise keep priority for advances made before a lien is preserved or written notice is received.
Two further rules matter for exits. A purchaser from a mortgagee takes title free of the special priority under ss. 78(2) and (5) if a prescribed bond, letter of credit or guarantee from a Schedule I or II bank is registered on title (s. 78(10)). And a mortgage given or assumed by a home buyer is outside the building mortgage and holdback-deficiency rules (s. 78(11)).
| Situation | Rule | Lender risk |
|---|---|---|
| Mortgage taken to finance the improvement | s. 78(2): liens rank ahead to extent of holdback deficiency | High if holdbacks not retained |
| Mortgage registered before first lien; earlier advances | s. 78(3): priority up to lesser of value and amounts advanced | Valuation evidence needed |
| Prior mortgage; advance after first lien | s. 78(4): priority unless lien preserved or written notice received | Title and notice checks before each advance |
| Mortgage registered after first lien | ss. 78(5)–(6): subordinate to holdback deficiency; otherwise as above | Common for refinancings mid-project |
| Sale by mortgagee | s. 78(10): bond or bank LC removes special priority | Cost of security to clear title |
Holdbacks and the 2026 annual release regime
Every payer on a contract or subcontract under which a lien may arise must retain a holdback of 10% of the price of services or materials as actually supplied (s. 22(1)). The holdback is the fund that protects lien claimants, and the holdback deficiency is what drives the building mortgage subordination. For construction lending, the practical question is therefore whether the owner is actually holding back and paying it out properly.
From 1 January 2026, Ontario requires mandatory annual release of holdback (s. 26, as replaced by 2024, c. 20, Sched. 4). Following each anniversary of the contract, the owner must publish a notice of annual release within 14 days specifying the amount it intends to pay, and must pay the accrued holdback for the preceding year at least 60 but not more than 74 days after the notice, unless a lien has been preserved or perfected and not dealt with. Contractors must then pay subcontractors' holdback within 14 days. Lenders need to fund these releases on schedule and confirm that no liens are outstanding before each annual release is paid.
Holdbacks sit alongside the statutory trust. Amounts owing to or received by contractors and subcontractors on account of the price of an improvement form a trust fund for the benefit of those who supplied services or materials (s. 8), and trustees must deposit trust funds into a bank account and keep records (s. 8.1). The owner has a parallel trust: amounts it receives to finance the improvement, including amounts it must retain as holdback, form a trust fund for the contractor, subject to payment of the land price and prior encumbrances (s. 7(1)). Lenders should make sure their advance mechanics do not collide with those trusts, for example by sweeping project funds to pay unrelated debts.
Advances, lien searches and cost-to-complete tests
A well-run construction loan ties every advance to evidence that the project is on budget, that trades have been paid and that holdbacks are intact. Standard conditions include:
- a cost consultant's report certifying work completed, the cost to complete and that the remaining loan plus equity is sufficient;
- statutory declarations from the owner and general contractor that trades have been paid, with supporting invoices;
- evidence that the owner has retained the 10% holdback, often through a separate holdback account controlled by the lender;
- a sub-search of title immediately before each advance to confirm that no claim for lien or certificate of action has been registered, and confirmation that the lender has not received written notice of a lien; and
- title insurance with a construction lien endorsement, often on a pending-disbursement basis.
The cost-to-complete test protects against the most common construction lending failure: an over-budget project where the last advances go to pay overruns while trades remain unpaid. If the test fails, the borrower must inject equity before the next advance. Lenders also set retention on their own advances that mirrors the statutory holdback, so that the funds to pay holdback releases exist when they fall due.
Under s. 78(4) and (6), a lender loses priority for advances made after it receives written notice of a lien. Make sure the notice address in the loan documents reaches the construction lending team quickly, and build a hard stop into the funding workflow when any lien notice arrives, however small the claim.
Construction lending in other provinces
Other common-law provinces follow the same broad model of holdback, lien and priority, but the details differ. Holdback percentages, lien periods, prompt payment regimes and the treatment of building mortgages vary, and some provinces have recently overhauled their statutes. Alberta and several other provinces have adopted prompt payment and adjudication regimes, and British Columbia uses its own Builders Lien Act framework, while Alberta's regime is in the Prompt Payment and Construction Lien Act. Quebec relies on legal hypothecs in favour of construction participants under the Civil Code, with registration and notice requirements that differ from the common-law lien model.
For national lenders, this means a single construction lending template is not enough. Loan agreements, holdback controls and advance checklists should be adapted to each province where projects are financed, and local counsel should confirm the lien periods and registration mechanics.
Protections in construction loan agreements
Beyond advance conditions, construction loan agreements should include:
- Holdback covenants. A covenant to retain and administer holdbacks, publish notices and pay annual releases in compliance with the Act.
- Lien covenants. An obligation to discharge or vacate any registered lien within a short period, by payment or by posting security in court.
- Assignment of construction contracts and consents from the general contractor and key consultants allowing the lender to step in.
- Performance and labour and material payment bonds from a licensed surety, naming the lender as an obligee or beneficiary.
- Completion guarantees and cost overrun guarantees from sponsors.
- Information rights covering schedule, change orders, disputes and adjudication notices under the prompt payment regime.
- Events of default tied to unpaid trades, lien registrations, stoppage of work and failure of cost-to-complete tests.
Ontario's prompt payment rules also affect cash flow: an owner must pay a proper invoice within 28 days unless it gives a notice of non-payment (s. 6.4), and contractors must pay subcontractors within seven days of being paid (s. 6.5). Lenders should align their funding timetable with these deadlines, because late advances can push the owner into breach and invite adjudication.
Refinancings, take-outs and mezzanine debt
Mid-project refinancings deserve particular care. A replacement lender that registers after the first lien arose falls under ss. 78(5) and (6): it ranks behind liens to the extent of any holdback deficiency, and its priority for each advance depends on title and notice checks at the time. A mortgage taken to repay a building mortgage inherits the building mortgage's subordination under s. 78(2). The new lender should therefore obtain an up-to-date holdback reconciliation, statutory declarations and a cost consultant's review before it funds, and should require that any shortfall be cured from the advance itself.
Mezzanine and second-ranking lenders face the same lien risk, plus subordination to the senior lender. Their intercreditor agreement should require the senior lender to enforce holdback controls, give the mezzanine lender notice of lien registrations and cost overruns, and preserve the mezzanine lender's right to cure or buy out the senior loan before enforcement.
When the project fails
If a development stalls, construction liens, trust claims and holdback deficiencies become the core priority dispute in any receivership. A court-appointed receiver or a trustee under Part IX of the Construction Act may need to borrow to complete or preserve the project; advances to a Part IX trustee rank ahead of liens existing at the trustee's appointment (s. 78(7)). Lenders should model their recovery net of likely holdback deficiencies and lien claims, not just the appraised value of the land. Our note on distressed real estate and construction insolvency covers enforcement in more detail.
How TRW & Co helps
We advise banks, private lenders, mortgage investment corporations and developers on construction lending across Canada. We draft and negotiate construction loan agreements, holdback and advance mechanics, intercreditor arrangements with mezzanine lenders, and contractor and surety consents, and we advise on priority disputes and enforcement when projects fail. We work with Canadian real estate counsel and cost consultants where local registration or certification is required. See our pages on construction law and lending and acquisition finance, and our note on mortgage brokering and private lending. This is general information, not legal advice. To discuss a construction lending question, contact us.
Frequently asked questions
What is a building mortgage under the Ontario Construction Act?
It is a mortgage taken with the intention of securing the financing of an improvement. Under s. 78(2), liens arising from that improvement rank ahead of the building mortgage, and any mortgage that refinances it, to the extent of any deficiency in the holdbacks the owner was required to retain, regardless of when the mortgage was registered.
Does written notice of a lien affect later advances?
Yes. Under ss. 78(4) and (6), advances keep priority over unpreserved liens only if, when the advance is made, no lien has been preserved or perfected against the premises and the lender has not received written notice of a lien. Lenders should search title and check for notices immediately before every advance.
What changed for holdbacks in 2026?
From 1 January 2026, Ontario requires annual release of holdback. After each anniversary of the contract, the owner must publish a notice within 14 days and pay the accrued holdback for the prior year 60 to 74 days later, unless a preserved or perfected lien has not been dealt with. Contractors then pay subcontractors within 14 days.
How can a lender sell a project free of the special lien priority?
Section 78(10) lets a purchaser from a mortgagee take title free of the special priority under ss. 78(2) and (5) if a bond from a licensed surety, or a letter of credit or guarantee from a Schedule I or II bank, in the prescribed form is registered on title. Lien claimants then look to that security instead.
Sources
General information only, not legal advice. References to statutes, courts and authorities describe published law and practice at the date shown.