Distressed Real Estate and Construction Insolvency in Canada
Distressed real estate projects bring lenders, condominium purchasers, lien claimants and governments into conflict. Lenders can use power of sale, a court-appointed receiver or support a CCAA or proposal. This note explains each route in Ontario, the Condominium Act deposit trust, Construction Act liens and trusts, and how partly built projects are sold.

Key takeaways
- Ontario power of sale requires 15 days' default and 35 days' notice before sale.
- Court receivers can borrow on priority charges and convey title by vesting order.
- Condominium Act s. 81 requires purchaser deposits to be held in trust or secured.
- Construction Act liens, holdbacks and trusts must be resolved before sale proceeds are distributed.
- Bidders for partly built projects decide whether to assume or terminate pre-sale agreements.
Enforcement options for distressed real estate
Distressed real estate projects in Canada usually end in one of three ways: a lender's power of sale, a court-appointed receivership, or a restructuring under the Companies' Creditors Arrangement Act (CCAA) or a proposal under the Bankruptcy and Insolvency Act (BIA). Each route treats the stakeholders of a development differently. Lenders want speed and control, purchasers of pre-sold condominium units want their deposits and their homes, contractors and trades want to be paid from statutory trusts and holdbacks, and municipalities and governments want taxes and development charges. Choosing the right route early determines how much value survives.

This note focuses on Ontario, where the volume of condominium and rental development has made distressed real estate a major part of insolvency practice, and covers power of sale, court receivers, CCAA filings by developers, condominium deposit trusts and new home warranty protection, construction lien claimants and trust funds, and how partially built projects are sold.
Power of sale versus a court-appointed receiver
A mortgagee under a charge with a power of sale can sell the property privately without going to court. In Ontario, the Mortgages Act requires that the default have continued for at least 15 days before notice of sale is given, and that the sale not occur until at least 35 days after notice (s. 32). Power of sale is fast and inexpensive for completed or vacant properties, but it has limits for active developments: the mortgagee must sell at fair market value after proper marketing, it does not clear lien claims and deposit trust issues in the way a vesting order does, and taking possession of an active site exposes the mortgagee to operating and construction risks.
A court-appointed receiver under s. 243 of the BIA, or under provincial courts of justice legislation, can take possession, complete or preserve the project, borrow on a priority charge, run a court-approved sale process and convey title by an approval and vesting order that clears registered interests and liens. A secured creditor enforcing against all or substantially all of an insolvent debtor's property generally must first give ten days' notice under s. 244. Receiverships cost more, but for partly built projects with many stakeholders they usually produce cleaner titles and fewer challenges.
| Route | Best suited to | Advantages | Limitations |
|---|---|---|---|
| Power of sale | Completed or vacant property; single lender | Speed, low cost, lender control | No vesting order; lien and deposit issues remain; possession risk |
| Court-appointed receiver | Partly built projects; multiple stakeholders | Court supervision, borrowing charge, vesting order | Cost; court timelines |
| CCAA or BIA proposal | Developers with several projects or viable business | Stay, interim financing, plan or sale | Requires debtor cooperation and a viable path; monitor costs |
CCAA filings by developers
Developers with multiple projects sometimes file under the CCAA to stabilize the whole group, keep sites running and negotiate with lenders project by project. Courts have accepted CCAA proceedings for real estate groups where there is a genuine restructuring purpose, but they look closely at whether the filing is simply a way to delay mortgage enforcement on single-purpose entities. Lenders frequently respond by seeking to carve their projects out of the CCAA or to convert the proceeding into a receivership for their collateral. Where projects are cross-collateralized or share financing, a group-wide process can make more sense.
The monitor's role is particularly important in these cases. It reports on cash flow by project, flags any use of one project's funds to support another, and helps the court decide whether particular projects should be carved out for lender enforcement. Purchasers of units, trades and municipalities often rely on the monitor's reports to understand what is happening on their site, so transparent project-level reporting reduces disputes and objections. Interim financing for a developer group is also usually allocated project by project, with charges limited to the assets of the project that benefits.
Condominium deposit trusts and new home warranty protection
Purchasers of pre-construction condominium units pay deposits that the Condominium Act, 1998 requires to be held in trust. Under s. 81(1), the declarant must ensure that a prescribed trustee or the declarant's solicitor receives and holds in trust all deposits on reservation, agreements of purchase and sale and sales of proposed units, together with interest. The trust continues, even after registration of the declaration, until the money is disposed of in accordance with the Act and the purchase agreement, or until the declarant provides security of a prescribed class for it, typically deposit insurance (s. 81(7)).
In a developer's insolvency, properly trusted deposits are not available to the developer's creditors. Where deposits have been released against deposit insurance or other prescribed security, purchasers look to that security. Ontario's new home warranty program, administered by Tarion, also provides limited deposit protection for purchasers of new homes and condominium units, subject to caps and conditions. Receivers must decide whether to complete the project and close sales, or to terminate agreements and return deposits; the choice depends on whether existing pre-sale prices still make completion viable. Courts have approved receivers' requests to disclaim pre-sale agreements where completion at the original prices would harm creditors, while requiring that purchasers' deposits be protected and returned.
At the start of any distressed condominium file, obtain a reconciliation of every purchaser deposit: where it is held, whether it was released against deposit insurance and which insurer issued the security. Deposit questions drive purchaser objections and media attention, and resolving them early protects the sale process.
Lien claimants, holdbacks and trust funds
Contractors, subcontractors and suppliers on a distressed project are protected by Ontario's Construction Act. They can register liens against the owner's interest; the owner must retain a 10% holdback (s. 22); money received by the owner to finance the improvement is impressed with a trust for the contractor (s. 7); and amounts received by contractors and subcontractors are trust funds for those below them (s. 8). A building mortgage ranks behind liens to the extent of any holdback deficiency (s. 78(2)). In receiverships, these claims are usually addressed by having the receiver hold back from sale proceeds an amount sufficient to cover registered liens and potential holdback deficiencies, and then running a court-supervised lien claims process.
Trust claims under the Construction Act can survive bankruptcy where the trust funds remain identifiable, so lenders and receivers must trace project funds carefully. Our note on construction lending and lien priority explains the priority rules in detail.
Selling partially built projects in distressed real estate files
Partly built developments are hard to value and hard to sell. Buyers discount for construction risk, cost overruns, expired permits, existing pre-sale agreements and unresolved lien claims. Receivers typically market the project through a broker with a defined process, allow bidders to choose whether to assume or terminate pre-sale agreements, and seek an approval and vesting order that conveys title free of registered charges and liens, with claims attaching to the proceeds. Development approvals, site plan agreements, letters of credit posted with municipalities and development charge credits need to be analysed for transferability, because they can carry significant value or cost.
Credit bids by the senior lender are common, particularly where the market for development land is weak and few buyers are active. Courts approve them where the process was fair and the lender's security is valid, but they look carefully at whether third-party bidders had a real opportunity to compete. In some cases, a reverse vesting order is used to preserve municipal approvals or tax attributes inside the project entity.
Operating income properties in receivership
Not all distressed real estate is under construction. Office buildings, rental apartments, retail centres and hotels with falling occupancy or refinancing gaps also end up in enforcement. For income properties, the receiver's first job is to stabilize operations: collect rents, keep property managers and service contractors in place, maintain insurance and deal with urgent capital repairs. Tenants generally continue to pay rent to the receiver, and residential tenants keep the protections of provincial residential tenancy legislation, which a receiver or purchaser must respect.
Leases matter to value. Purchasers will want estoppel certificates and attornment from tenants, and lenders will look at whether subordination, non-disturbance and attornment agreements were obtained when the loan was made. Where a property is partly vacant, the receiver may need court authority to sign new leases or grant inducements to improve the asset before sale. In distressed real estate cases involving multi-residential buildings, the receiver must also manage relationships with tenants and municipalities carefully, because repair orders and property standards issues can delay a sale.
Municipal taxes, development charges and government claims
Municipalities have significant leverage in real estate insolvencies. Unpaid realty taxes are typically a special lien on the land that ranks ahead of mortgages under provincial municipal legislation, and municipalities can ultimately sell land for tax arrears. Development charges, parkland and other levies may be payable at permit issuance, and unpaid amounts or security posted under development agreements can affect a buyer's ability to proceed. Federal and provincial claims, such as harmonized sales tax on new housing and source deductions for site employees, must also be analysed under the BIA's priority rules.
Receivers and lenders should obtain tax certificates, development agreement summaries and a list of municipal securities early, and should open discussions with the municipality about transferring approvals and securities to a purchaser. In a distressed real estate sale, a municipality's cooperation on these items can be worth as much as a price increase.
Practical checklist for lenders and purchasers
- Decide early between power of sale, receivership and supporting a CCAA or proposal, based on the project's stage and stakeholders.
- Reconcile purchaser deposits, deposit insurance and warranty enrolment.
- Obtain a title and lien search and a holdback reconciliation; budget for lien claims.
- Assess development approvals, municipal securities and permits for transferability.
- Commission a cost-to-complete report to evaluate completion versus sale as-is.
- Plan purchaser communications with the receiver or monitor, including a dedicated website and contact point.
- Confirm insurance, site security and environmental conditions before taking possession of an active site.
- Structure credit bids and vesting orders to deal with liens, deposits and municipal items.
How TRW & Co helps
We advise lenders, private credit funds, developers, purchasers and receivers' counsel teams on distressed real estate and construction insolvency in Canada. Our work includes enforcement strategy, receivership and CCAA applications, sale processes and credit bids, deposit and warranty issues, lien and trust claims, and acquisitions of partly built projects. We work with Canadian real estate counsel, licensed insolvency trustees and cost consultants where required. See our pages on receiverships and enforcement and construction law. This is general information, not legal advice. To discuss a distressed project, contact us.
Frequently asked questions
Should a lender use power of sale or a receiver for a stalled condo project?
For a completed or vacant property, power of sale is often faster and cheaper. For a partly built project with purchasers, trades and lien claims, a court-appointed receiver is usually better because it can borrow on a priority charge, run a supervised sale and convey title by vesting order that clears registered interests, with claims attaching to proceeds.
Are condominium deposits safe if the developer becomes insolvent?
Deposits must be held in trust under s. 81 of the Condominium Act, 1998 until disposed of in accordance with the Act or until prescribed security such as deposit insurance is provided. Properly trusted deposits are not available to the developer's creditors, and purchasers may also have limited protection through Ontario's new home warranty program.
What happens to construction liens when a project is sold by a receiver?
The receiver usually sells free and clear of liens under an approval and vesting order, with lien claims attaching to a reserve from the sale proceeds. A court-supervised claims process then determines valid liens and priority, including any holdback deficiency that ranks ahead of the building mortgage.
Can a receiver cancel pre-sale agreements?
Courts have permitted receivers to disclaim pre-sale agreements where completing them at the original prices would harm creditors, while ensuring that purchasers' deposits are protected and returned in accordance with the trust and any deposit insurance. Each case depends on the evidence and the stage of the project.
Sources
General information only, not legal advice. References to statutes, courts and authorities describe published law and practice at the date shown.