Developing Wind and Solar Projects: Land, Permits and PPAs

Wind and solar projects in Canada succeed or fail on a handful of early decisions: where the land is, who supports the project, which procurement or offtaker pays for the power and how quickly the grid can connect it. This guide walks through each step, from land options to Alberta’s 2024 rules, provincial tenders and PPAs.

Wind turbines and solar panels on farmland, illustrating development of wind and solar projects in Canada

Key takeaways

  • Alberta bars renewables on Class 1 and 2 farmland unless coexistence is shown, and requires reclamation security.
  • New wind projects are excluded from Alberta’s designated viewscape buffer zones.
  • IESO’s first LT2 energy window awarded 20-year contracts to 14 projects totalling 1,315 MW.
  • Hydro-Québec’s 2026 wind call seeks 5 to 10 TWh with 20- to 30-year contracts and municipal support.
  • Clean Technology and Clean Electricity ITCs remain central to project economics and financing.

How wind and solar projects get built in Canada

Developing wind and solar projects in Canada follows a predictable arc: secure land, earn local and Indigenous support, obtain provincial and municipal approvals, win a place in an interconnection queue, and sign a revenue contract that lenders will finance. What varies is the order and the gatekeeper. In Ontario and Quebec, revenue usually comes from a competitive provincial procurement, so the tender rules dictate how projects are designed. In Alberta's deregulated market, developers rely on merchant revenue or corporate power purchase agreements, and the province's 2024 land-use rules now decide where projects can go. Understanding those differences early saves money and avoids stranded development spending.

Wind turbines and solar panels on farmland, illustrating development of wind and solar projects in Canada
Wind and solar projects in Canada combine land agreements, provincial approvals, interconnection and long-term offtake.

Electricity is a provincial responsibility, so most approvals for wind and solar projects are provincial or municipal. Federal law becomes relevant where a project affects fish habitat, migratory birds, species at risk, navigable waters or federal lands, and federal investment tax credits are an important part of project economics.

Land: leases, options and easements

Most onshore wind and solar projects are built on private land under long-term leases or on Crown land under provincial dispositions. Developers usually start with option agreements that give them the right to lease land once permits and offtake are secured. Well-drafted options set the option term and fees, define the area that may be used, deal with access during studies, and convert automatically into a lease on exercise. The lease itself should run long enough to cover the offtake term plus construction and decommissioning, with renewal rights where possible.

Key lease terms for these projects include rent structure (fixed, per-megawatt or revenue-based), crop damage and drainage compensation, setbacks from residences, rights for collector lines and access roads, lender protection clauses, assignment to financing parties and end-of-life removal. Land registration practice differs by province: leases and easements should be registered or notice filed so that they bind successors and rank ahead of later mortgages. Where farmland is involved, lenders to the landowner may need to sign non-disturbance agreements.

Municipal and Indigenous support

Community support has become a formal requirement rather than a soft factor. Ontario's procurements score or require municipal support resolutions and Indigenous participation; the IESO reported that all 14 projects offered contracts in the first Long-Term 2 (LT2) energy window had Indigenous equity partnership. Hydro-Québec's 2026 wind call for tenders requires that each local municipality administering the project territory formally support the project, accepting a support "in principle" at bid stage, and asks for a social acceptability plan, a consultation plan and responses to concerns raised by Indigenous communities.

Indigenous partnerships take many forms: equity ownership, revenue sharing, procurement and employment commitments, environmental monitoring roles and capacity funding. Equity stakes are often financed with loan guarantees, discussed in our note on Indigenous equity ownership and loan guarantees. Separately, the Crown's duty to consult applies to provincial and federal decisions on the project, and proponents typically carry out much of the procedural work.

Alberta's land-use rules for wind and solar projects

Alberta paused new renewable approvals in 2023 and then adopted new policy in February 2024. According to the Government of Alberta's summary of policy changes (6 December 2024), the changes are implemented through the Electric Energy Land Use and Visual Assessment Regulation, amendments to the Activities Designation Regulation and the Conservation and Reclamation Regulation, and Alberta Utilities Commission (AUC) rule changes. The main elements are:

  • Agriculture first: renewable energy developments are no longer permitted on Land Suitability Rating System Class 1 and 2 lands unless the proponent shows that crops or livestock can coexist with generation; in municipalities without Class 1 or 2 lands, Class 3 lands are treated the same way; an irrigability assessment must be done and considered by the AUC.
  • Viewscapes: new wind projects are no longer permitted within designated buffer zones, and other electricity developments within buffer zones or visual impact assessment zones must submit a visual impact assessment.
  • Reclamation security: developers must provide mandatory security or a bond for reclamation, including on private land, either to the province or negotiated with landowners where the AUC accepts the evidence.
  • Municipalities: municipalities automatically have standing in AUC hearings and may seek cost recovery for participation.

Developers in Alberta should screen sites against soil class maps and buffer zone designations before signing options, budget for reclamation security from day one and plan for municipal participation in AUC proceedings. Our note on the Alberta electricity market restructuring covers the separate market reforms that affect revenue.

Provincial procurements: IESO and Hydro-Québec

The table compares the two largest current procurement channels for wind and solar projects in Canada, based on the procurers' own documents.

FeatureOntario — IESO LT2Quebec — Hydro-Québec A/O 2026-01 (wind)
TargetSeries of windows seeking 14 TWh of energy and 1,600 MW of capacity in total5 to 10 TWh of new wind energy, plus repowering volumes
Contract term20 years20 to 30 years
Results to dateEnergy window 1 (April 2026): 14 projects, 1,315 MW, 3.02 TWh, weighted average CAD 87.80/MWhUp to three rounds for new projects, with deliveries between 2031 and 2038
Community conditionsAll selected projects had Indigenous equity participation and were outside Prime Agricultural AreasFormal support from each local municipality; consultation and social acceptability plans
PriceFixed price per MWh, bid competitivelyPrice may be indexed to CPI or a fixed rate; formula cannot decrease over time

The IESO's LT2 results overview notes that the first energy window met its 3 TWh target with 12 solar and two wind projects and that 10 projects will be in Northern Ontario. Hydro-Québec's call materials explain that its process was redesigned after Quebec adopted its 2025 energy governance law, with a view to more predictability and flexibility. Our separate article on Hydro-Québec calls for tenders discusses Quebec's process in more detail.

Practical point

Procurement rules often prohibit or penalize changes after bid submission. Lock in land, interconnection assumptions, turbine or module supply and partnership terms before bidding, and make sure partnership agreements with municipalities and Indigenous Nations do not contain terms that limit competition, which Hydro-Québec states will lead to rejection.

Permits and environmental approvals

Permit requirements differ by province but usually include a provincial environmental approval or assessment, municipal land-use approvals, building permits, wildlife and heritage studies, and road use agreements. Wind projects face bird and bat studies and post-construction monitoring; solar projects often face drainage, glare and soil management conditions. In Alberta, the AUC approves power plants, substations and transmission, with input from Alberta Environment and Protected Areas on wildlife. Ontario projects need approvals under environmental legislation and municipal planning rules. Quebec projects may require an environmental impact assessment and authorization under the Environment Quality Act depending on size.

Federal approvals arise where a project triggers the Fisheries Act, the Species at Risk Act or the Migratory Birds Convention Act, or affects navigable waters. Our note on Fisheries Act authorizations and species at risk permits explains those processes.

Interconnection and revenue contracts

Interconnection is the other long-lead item. In Alberta, the AESO connection process sets study stages, cost estimates and security requirements; in Ontario, the IESO and Hydro One or local distributors handle system impact and customer impact assessments; in Quebec, Hydro-Québec's transmission division specifies connection requirements and carries out studies as part of the call for tenders. Connection agreements allocate upgrade costs and set in-service dates, so they should be aligned with offtake milestones.

Where there is no provincial procurement, or alongside one, developers sign corporate power purchase agreements. In Alberta these are often virtual PPAs settled against the pool price. Key terms include contract quantity, settlement price, environmental attributes, curtailment, change in law and credit support. Our guide to corporate PPAs and virtual PPAs covers drafting in depth.

Tax credits and financing of wind and solar projects

Federal investment tax credits are central to project economics. The Clean Technology ITC is refundable at up to 30 per cent for eligible property, and the Clean Electricity ITC is available at up to 15 per cent, with prevailing wage and apprenticeship conditions for the full rate. Budget 2026 proposes extending both credits to property available for use before 2041; that remains a proposal until enacted. Lenders will test credit eligibility, labour compliance and the allocation of credits within partnership structures.

Project finance for renewables typically combines construction loans that convert to term debt, tax equity-style structures where credits are monetized, and sponsor or Indigenous equity. Financing documents will require assignment of land rights, offtake and connection agreements, direct agreements with counterparties and robust insurance. See our page on project and infrastructure finance.

Allocating development risk in wind and solar projects

Most disputes in renewable developments arise from risks that were foreseeable but not allocated. A short list of recurring issues helps structure negotiations with landowners, contractors, offtakers and partners:

  • Permit delay: who bears the cost if approvals take longer than expected, and whether option terms and procurement milestones can be extended.
  • Interconnection cost overruns: whether the offtake price can be adjusted, or the project abandoned, if upgrade estimates rise sharply after studies.
  • Curtailment: whether the offtaker or procurer pays for energy that cannot be delivered because of grid constraints or economic dispatch.
  • Supply chain and tariffs: how changes in duties on modules, turbines or steel are treated, particularly given recent trade measures between Canada and the United States.
  • Change in law: whether new provincial land-use rules, market redesign or federal measures permit price adjustments or termination.
  • Decommissioning: who funds removal and reclamation at the end of the project, and how that obligation survives a sale.

Acquisitions and repowering

Many investors enter the market by acquiring operating or late-stage renewable assets rather than developing from scratch. Due diligence should confirm that land rights cover the full contract term, that permits and connection agreements are transferable, that change-of-control clauses in offtake and partnership agreements have been addressed, and that any Indigenous partner's consent or rights of first refusal are respected. For older wind farms whose contracts are expiring, repowering raises new questions: whether existing permits cover larger turbines, whether leases allow new layouts and whether the project can compete in a new procurement. Hydro-Québec's 2026 call includes specific rounds for repowering projects, showing that procurers now treat repowering as a distinct pathway.

How TRW & Co helps

We advise developers, independent power producers, investors, lenders and Indigenous partners on wind and solar projects across Canada. We draft and negotiate land options and leases, partnership and benefit agreements, procurement bids and contracts, connection agreements and corporate PPAs, review permitting strategies and assess tax credit eligibility and financing structures. Where a step requires a lawyer licensed in the relevant province, we coordinate with local counsel. This article is general information, not legal advice. To discuss a project, contact us.

Frequently asked questions

Can wind and solar projects be built on farmland in Alberta?

Not on Land Suitability Rating System Class 1 and 2 lands unless the proponent shows that crops or livestock can coexist with the generation project. In municipalities without Class 1 or 2 lands, Class 3 lands are treated the same way, and an irrigability assessment must be done and considered by the Alberta Utilities Commission.

How long are Ontario and Quebec renewable energy contracts?

The IESO’s Long-Term 2 procurement offers 20-year contracts. Hydro-Québec’s 2026 wind call for tenders allows contract terms of 20 to 30 years. In both cases contract terms, pricing mechanisms and milestones are set by the procurement documents, so bidders should read the final versions and any addenda.

Do renewable projects need Indigenous partners?

Not always as a legal requirement, but partnerships are increasingly expected and can be scored or required in procurements. All 14 projects selected in the IESO’s first LT2 energy window had Indigenous equity participation. Separately, the Crown’s duty to consult applies to government approvals, and proponents often carry out procedural aspects.

What federal approvals can apply to wind and solar projects?

Most approvals are provincial and municipal, but federal requirements can arise under the Fisheries Act, the Species at Risk Act, the Migratory Birds Convention Act and navigable waters legislation, or where federal lands are involved. Federal investment tax credits also affect project design and labour practices.

What is reclamation security in Alberta?

Alberta requires developers of renewable energy operations to provide mandatory security or a bond covering reclamation costs, including for projects on private land. The security is either provided to the province or negotiated with landowners if the AUC accepts sufficient evidence. It should be budgeted from the start of development.

Sources

  1. Government of Alberta — Summary of Policy Changes for renewable power development (6 Dec 2024)
  2. IESO — Results of the Long-Term 2 Window 1 Energy Stream (April 2026)
  3. Hydro-Québec — Conférence préparatoire, A/O 2026-01 (28 April 2026)
  4. Budget 2026 — Tax Measures: Supplementary Information

General information only, not legal advice. References to statutes, courts and authorities describe published law and practice at the date shown.