LNG Export Licences and Approvals in Canada
LNG export licences from the Canada Energy Regulator are only one of the approvals an LNG project needs. This note explains the federal licensing test and timelines, BC Energy Regulator facility permits, provincial climate conditions, impact assessment by substitution, Indigenous ownership models and the key terms of LNG offtake contracts.

Key takeaways
- LNG export licences are issued by the CER Commission with ministerial approval under s. 344 of the CER Act.
- Natural gas export licences can run for up to 40 years and require a surplus finding under s. 345.
- The Commission decides within 180 days of a complete application; the Minister then has 90 days.
- BC's Energy Action Framework expects new LNG facilities to have a credible plan to be net zero by 2030.
- Ksi Lisims LNG was approved in September 2025 after a BC assessment substituted for the federal one.
What LNG export licences and approvals a project needs
An LNG export project in Canada needs approvals at two levels. Federally, LNG export licences are issued by the Canada Energy Regulator (CER) Commission, with the Minister's approval, under s. 344 of the Canadian Energy Regulator Act; a natural gas export licence can run for up to 40 years. Provincially, in British Columbia, the liquefaction facility itself is permitted by the BC Energy Regulator, an environmental assessment certificate is usually required, and the province's climate policy shapes what can be built. Large terminals may also need a federal impact assessment, a Fisheries Act authorization and marine approvals.

This note sets out the federal export licensing process, the BC facility permitting regime and climate conditions, the role of impact assessment, Indigenous ownership models, and the main terms of LNG offtake contracts. It reflects legislation consolidated to October 2026 and government releases cited below.
How the CER grants LNG export licences
Exports of oil and gas require a licence or an order under Part 7 of the CER Act. For long-term LNG exports, proponents apply for a licence, which the Commission may issue with the Minister's approval and subject to conditions (s. 344(1)). The core statutory test is surplus: under s. 345, the Commission must be satisfied that the quantity to be exported does not exceed the surplus remaining after allowance for reasonably foreseeable Canadian requirements, having regard to trends in discovery.
| Step | Rule | CER Act |
|---|---|---|
| Commission decision | Within 180 days after a complete application, subject to excluded periods | s. 346 |
| Minister's approval | Within 90 days after the Commission's decision | s. 347(1) |
| Issuance | Within seven days after ministerial approval | s. 347(3) |
| Term | Maximum 40 years for natural gas export licences | Regulations-making power and maximum validity provision in Part 7 |
| Variation and transfer | Commission may vary or transfer; ministerial approval needed unless minor or technical | ss. 348–349 |
| Suspension and revocation | On consent, for breach of conditions, or in the public interest with ministerial approval | ss. 350–351 |
Licences typically specify the export point, maximum annual and term quantities, a tolerance, and a "sunset" by which exports must begin. Because liquefaction projects take years to reach a final investment decision, proponents often need to vary licences to extend start dates or adjust volumes; the Commission can approve minor and technical variations itself, while others need the Minister's approval. Short-term exports can proceed under orders rather than licences.
BC Energy Regulator facility permits
In British Columbia, LNG facilities are regulated by the BC Energy Regulator (BCER) under the Energy Resource Activities Act as energy resource activities. The BCER issues the facility permit covering design, construction and operation, and also regulates the upstream wells, processing plants and provincially regulated pipelines that feed the terminal. Permits address safety, emergency management, environmental protection and decommissioning, and the BCER inspects and enforces compliance.
Major LNG facilities also need an environmental assessment certificate from the BC Environmental Assessment Office, along with water, land tenure and other provincial authorizations. Municipal and regional approvals may be needed for associated infrastructure. Feed gas pipelines that cross a provincial border fall under the CER instead; see our note on pipeline approvals.
Climate conditions and federal impact assessment
Provincial climate policy
In its Energy Action Framework of 14 March 2023, the BC government said proposed LNG facilities in or entering environmental assessment must pass an emissions test requiring "a credible plan to be net zero by 2030", using best-in-class technology and verified offsets for remaining emissions (BC news release). In practice this has pushed projects toward electric-drive liquefaction powered from the grid or renewable sources, which in turn depends on transmission and supply arrangements with BC Hydro. Proponents should confirm how the province currently applies the framework, as provincial climate policy continues to evolve.
Federal impact assessment
Under the Physical Activities Regulations, a new facility for liquefaction, storage or regasification of LNG with processing capacity of 3,000 t/day or more, or storage of 136,000 m³ or more, is a designated project under the Impact Assessment Act; a new marine terminal for ships over 25,000 DWT may also be caught.
BC and Canada use substitution so that one assessment serves both levels. On 15 September 2025, the federal Minister issued a decision statement approving the Ksi Lisims LNG project, proposed by the Nisga'a Nation with Rockies LNG and Western LNG, after an assessment conducted by BC's Environmental Assessment Office under the IAA's substitution provisions — described as the first substituted assessment under the amended IAA (Impact Assessment Agency release). See our note on designated projects.
Federal climate rules also apply. LNG facilities are covered by industrial carbon pricing in BC, by federal methane regulations upstream, and potentially by future federal oil and gas emissions measures; our notes on industrial carbon pricing and methane regulations explain the current position.
Indigenous ownership models
Canadian LNG has seen a shift from benefit agreements toward Indigenous ownership. Models include:
- Indigenous-led proponents: projects such as Ksi Lisims, where a First Nation is a proponent and owner alongside industry partners, and Cedar LNG, a floating LNG project led by the Haisla Nation in partnership with a midstream company.
- Equity in pipelines and infrastructure: Indigenous partnerships acquiring stakes in feed gas pipelines, power supply or marine infrastructure, often financed through federal or provincial loan guarantee programs.
- Impact benefit agreements: revenue sharing, procurement, employment and environmental monitoring commitments, frequently alongside equity options.
Ownership changes the governance and financing of the project: shareholder agreements must address decision rights, funding obligations during construction, distribution waterfalls and exit rights, while lenders will look at the credit support behind each partner's equity. See our notes on Indigenous equity and loan guarantees and impact benefit agreements.
Offtake contracts and LNG export licences
LNG projects are financed on long-term sale and purchase agreements (SPAs) or tolling agreements. Key terms include:
- Structure: integrated sales (the project buys feed gas and sells LNG) versus tolling (customers supply gas and pay a liquefaction fee).
- Price: indexation to Henry Hub, Asian benchmarks or oil, plus a fixed liquefaction charge; price review clauses.
- Volume and flexibility: annual contract quantity, take-or-pay obligations, downward quantity tolerance and destination flexibility.
- Delivery: free on board at the Canadian terminal or delivered ex-ship; shipping arrangements and cargo scheduling.
- Conditions precedent: final investment decision, regulatory approvals (including the CER export licence and its variations), and financing.
- Change in law and carbon costs: allocation of new carbon pricing, emissions caps and other regulatory costs between seller and buyer.
- Disputes: international arbitration, typically seated outside Canada for Asian buyers.
Align the export licence with the SPAs. The licence's maximum annual quantity, term and commencement date should accommodate contracted volumes, tolerances and any expansion trains. Build licence variation risk into the conditions precedent and long-stop dates of offtake contracts.
Maintaining LNG export licences over the project life
Obtaining LNG export licences is the start of a long regulatory relationship. Licence holders must comply with reporting conditions, including reports on export volumes and destinations, and must keep the licence aligned with the project as it evolves. Common triggers for a variation include a delayed final investment decision that puts the export start date at risk, a change in the number or size of liquefaction trains, and a change of export point. Because licences typically include a sunset condition under which they lapse if exports have not begun by a set date, developers should track that date against the construction schedule and apply for any extension well before it arrives.
Changes in ownership matter too. A transfer of the licence to a new project entity requires the Commission's approval under s. 349, with the Minister's approval if the transfer is more than minor or technical. Upstream changes of control of the licence holder should be reviewed against the licence conditions and against foreign investment review requirements, since LNG facilities are critical energy infrastructure.
The surplus test in s. 345 has historically been met with evidence of Canada's large natural gas resource base, but proponents still need a supply and market study showing that the exported quantities will not compromise domestic needs. Where LNG export licences are sought for very large volumes or several projects at once, the Commission may examine cumulative export levels, and interveners may test the supply evidence.
East Coast and other export routes
Most Canadian LNG development is on the Pacific coast, which offers shorter shipping routes to Asian buyers, but East Coast proposals have resurfaced, focused on European demand. An Atlantic project raises different questions: feed gas would come either from Western Canada through long-haul pipelines or from offshore or imported sources, provincial approval regimes differ, and impact assessment and marine approvals follow the Atlantic provinces' frameworks. The federal export licensing test and process are the same nationwide, so LNG export licences remain the common federal step for any coast.
Practical roadmap for LNG proponents
- Apply early for LNG export licences, with volumes sized to future expansions.
- Engage the BC Environmental Assessment Office and the Impact Assessment Agency on substitution.
- Design the facility to meet provincial emissions expectations, including power supply.
- Build Indigenous ownership or partnership into the project structure from the outset.
- Secure feed gas, pipeline capacity and offtake in parallel with approvals.
- Plan for foreign investment review of investors and offtakers taking equity.
Illustration: a proponent plans a 2 million tonnes per annum floating LNG project on the BC coast. It applies to the CER for a 40-year export licence covering 3 million tonnes per annum to allow for expansion, obtains a BCER facility permit and a provincial environmental assessment certificate substituted for the federal assessment, and signs 20-year free-on-board SPAs whose conditions precedent include the licence and final investment decision.
Project finance lenders will review the full approvals package before financial close. They expect LNG export licences, the facility permit, the environmental assessment certificate and decision statement, water and land tenure, marine approvals and feed gas pipeline approvals to be issued and final, or to have a clear path with conditions that the project can meet. Conditions with cost or schedule implications, such as emissions limits, electrification commitments or Indigenous monitoring programs, should be priced into the base case. Lenders also review change-in-law protection in the SPAs and the sponsors' ability to fund cost overruns.
How TRW & Co helps
We advise LNG developers, Indigenous partners, offtakers, investors and lenders on LNG export licences, facility approvals and commercial contracts. We map approval pathways, review licence and permit conditions, structure Indigenous ownership and partnership arrangements, and negotiate SPAs, tolling agreements and gas supply contracts. We coordinate with Canadian-licensed regulatory counsel where hearings or filings require it. This work connects with our oil, gas and LNG and project finance practices. To discuss a project, contact us.
Frequently asked questions
Who issues LNG export licences in Canada?
The Commission of the Canada Energy Regulator issues LNG export licences with the approval of the federal Minister under s. 344 of the CER Act. The Commission must be satisfied that the exported quantity does not exceed Canada's surplus after reasonably foreseeable domestic needs. Licences for natural gas exports can last up to 40 years.
How long does a CER export licence take?
The Commission must decide within 180 days after it considers the application complete, subject to excluded periods. The Minister must then decide whether to approve within 90 days, and the Commission issues the licence within seven days of approval.
Does an LNG terminal need a federal impact assessment?
A new liquefaction, storage or regasification facility with processing capacity of 3,000 tonnes per day or more, or storage of 136,000 cubic metres or more, is a designated project. In British Columbia, the provincial environmental assessment can be substituted for the federal assessment, as happened for Ksi Lisims LNG.
Can an export licence be changed after it is issued?
Yes. The Commission may vary or transfer a licence, and needs the Minister's approval unless the change is minor or technical. Proponents often seek variations to extend start dates or adjust volumes as projects move toward a final investment decision.
Sources
- Canadian Energy Regulator Act, Part 7, ss. 344–351 (Justice Laws)
- Physical Activities Regulations, SOR/2019-285 (Justice Laws)
- Impact Assessment Agency: federal government green lights Ksi Lisims LNG (15 September 2025)
- BC Government: Energy Action Framework news release (14 March 2023)
- Energy Resource Activities Act, SBC 2008, c. 36
General information only, not legal advice. References to statutes, courts and authorities describe published law and practice at the date shown.