Pipeline Approvals at the Canada Energy Regulator
Pipeline approvals for interprovincial and international lines come from the Canada Energy Regulator and, for major projects, the federal Cabinet. With pipelines removed from the Impact Assessment Act Project List in September 2026 and Pacific Link listed as a national interest project, this note explains the current process, conditions, tolls and abandonment funding.

Key takeaways
- Major pipeline certificates need a CER Commission report and a Governor in Council decision under ss. 183–186.
- The Commission's report is due within 450 days of a complete application; Cabinet has 90 days, both extendable.
- Since 3 September 2026, interprovincial pipelines are no longer designated projects under the IAA.
- Tolls must be just and reasonable, and abandonment requires the Commission's leave.
- Pacific Link was listed under the Building Canada Act on 1 October 2026, with conditions targeted for September 2027.
How federal pipeline approvals work
Pipelines that cross a provincial or national border are federal works, and pipeline approvals for them come from the Canada Energy Regulator (CER) under the Canadian Energy Regulator Act (CER Act). For a major line, the CER's Commission holds a hearing, reports to the Minister with a recommendation and proposed conditions, and the Governor in Council decides whether the Commission must issue a certificate of public convenience and necessity (ss. 183–186). Smaller facilities — including pipelines of 40 km or less — can be approved by Commission order without Cabinet involvement (s. 214). Since 3 September 2026, interprovincial and international pipelines are no longer on the Impact Assessment Act Project List, so the CER is the single federal reviewer unless a project is listed under the Building Canada Act.

This note covers applications, hearings and timelines, conditions, tolls and tariffs, abandonment funding and liability, and the federal–Alberta framework that produced the first national interest listing, a new West Coast oil pipeline. It reflects the CER Act as consolidated to 19 October 2026 and government releases to October 2026.
Applications and hearings
An applicant for a certificate files its application with a map showing the general location of the pipeline and the plans and information the Commission requires, and gives notice to the attorney general of each province concerned (s. 182). The CER's filing manual sets out the detailed content: project description, engineering and safety, environmental and socio-economic assessment, Indigenous and public engagement, economic feasibility, supply and markets, and financing. Early engagement with the CER on the scope of the hearing, the list of issues and participant funding reduces the risk of completeness disputes.
The Commission decides who may participate, sets the hearing process (written, oral or hybrid) and can hold Indigenous oral traditional evidence sessions. Any member of the public may make representations in the manner the Commission specifies (s. 183(3)). Landowners along the route have separate rights in the detailed route approval process, including the right to object to the detailed route and to seek compensation through negotiation, mediation or arbitration.
The s. 183 recommendation and Cabinet decision
Once the application is complete, the Commission must prepare and publish a report recommending whether a certificate should issue, "taking into account whether the pipeline is and will be required by the present and future public convenience and necessity", and setting out all the conditions it considers necessary, regardless of its recommendation (s. 183(1)). Section 183(2) lists the factors, including:
- environmental effects, including cumulative effects, and safety and security;
- health, social and economic effects;
- the interests and concerns of Indigenous peoples and effects on their s. 35 rights;
- the availability of supply, actual or potential markets and economic feasibility;
- the applicant's financial resources and structure, and Canadian participation in financing, engineering and construction;
- the extent to which the pipeline hinders or contributes to Canada's environmental obligations and climate commitments; and
- any public interest the Commission considers may be affected.
| Stage | Rule | CER Act |
|---|---|---|
| Commission report | Within the time limit set by the Lead Commissioner, no longer than 450 days after a complete application, subject to excluded periods and ministerial extensions | s. 183(4)–(6) |
| Cabinet decision | Direct issuance with the report's conditions, refer back for reconsideration, or direct dismissal; within 90 days after the report, extendable | s. 186(1), (3) |
| Reasons | Order must show Cabinet took the relevant s. 183(2) considerations into account | s. 186(2) |
| Judicial review | Federal Court of Appeal, with leave; application within 15 days after Gazette publication of the order | s. 188 |
| Small pipelines | Exemption order route for pipelines of 40 km or less and certain facilities | s. 214 |
The Minister may direct timelines to keep the review moving (s. 183(8)). In practice, the most frequent delays arise from incomplete information on routing, Indigenous engagement and environmental baselines, and from reconsideration after judicial review. Pipeline approvals with a well-documented consultation record are significantly more robust on review.
Conditions and compliance
Certificates carry conditions on engineering, construction, environmental protection, emergency management, Indigenous monitoring and participation, reporting and, often, financial matters. Conditions survive into operations, and the CER enforces them through inspections, orders, administrative monetary penalties and prosecution. Certificates can later be varied or transferred, with Commission approval or, if the Minister so directs, a Governor in Council decision (s. 190). Buyers of pipeline assets should review outstanding conditions and compliance history carefully, as they travel with the certificate.
Negotiate conditions during the hearing, not after. The Commission must set out its proposed conditions in the s. 183 report, and Cabinet can only accept them, refer them back or dismiss. Applicants should test each draft condition for feasibility, cost and schedule impact and propose workable alternatives on the record.
Tolls, tariffs and abandonment funding
Tolls and tariffs
Part 3 of the CER Act gives the Commission authority over tolls and tariffs: companies must file tariffs, tolls must be just and reasonable (s. 230), and unjust discrimination in tolls, service or facilities is prohibited (s. 235). Most major oil pipelines are underpinned by long-term firm service contracts with shippers, often with a portion of capacity reserved for uncommitted spot shippers. The toll methodology, the treatment of capital cost overruns and the allocation of risk between committed shippers and the company are usually agreed in transportation service agreements and approved by the CER, sometimes after a contested hearing.
Abandonment and financial resources
A company must not abandon a pipeline without the Commission's leave (s. 241). Under the CER's financial regulatory framework, pipeline companies must estimate abandonment costs and set aside funds, typically through trusts, letters of credit or surety bonds, so that money is available when lines are retired. Separately, companies must maintain financial resources sufficient to cover their absolute liability for releases (s. 138); for companies operating oil pipelines with capacity of at least 250,000 barrels per day, the statutory limit is $1 billion (s. 137(5)).
Expansions, acquisitions and existing pipeline approvals
Not every project needs a new certificate. Many expansions — added pump or compressor stations, looping of existing lines, or short laterals — proceed under s. 214 orders, which the Commission can grant for pipelines of 40 km or less and for tanks, compressors, pumps and other connected works. These pipeline approvals are faster and do not require a Cabinet decision, but they still attract environmental, engineering and Indigenous engagement requirements, and the Commission may hold a hearing where issues warrant it.
Acquirers of federally regulated pipelines need the Commission's approval to transfer a certificate (s. 190) and, depending on the structure, approvals for purchase of the line by another company and for the transfer of tariffs and service agreements. Due diligence should cover existing pipeline approvals and their conditions, integrity management, abandonment cost estimates and set-aside mechanisms, outstanding compliance actions and the terms of firm service contracts. Foreign buyers should also consider the Investment Canada Act, including national security review, which applies to energy infrastructure; see our Investment Canada Act page.
For projects carrying products other than oil and gas, such as hydrogen or carbon dioxide, proponents should check whether the line falls within the CER Act's definition of a pipeline and federal jurisdiction, or remains provincial. The answer determines which regulator grants pipeline approvals and which safety and abandonment rules apply.
Pipeline approvals and the Impact Assessment Act
Until September 2026, interprovincial pipelines requiring 75 km or more of new right of way were designated projects under the Impact Assessment Act and had to be assessed by an integrated review panel. The Regulations Amending the Physical Activities Regulations (SOR/2026-185) removed international and interprovincial pipelines and other CER-regulated project types from the Project List with effect from 3 September 2026. The accompanying statement notes that no integrated panel review had ever been completed and that the CER Act already requires substantially the same factors to be considered. Pipeline approvals are now handled by the CER alone, or through the Building Canada Act for listed projects. See our note on designated projects.
The federal–Alberta framework for a West Coast pipeline
A new oil pipeline to the Pacific coast has been shaped by a series of federal–Alberta arrangements:
- Memorandum of understanding (27 November 2025): among other commitments, Canada agreed not to implement the oil and gas emissions cap and to suspend the Clean Electricity Regulations in Alberta pending an industrial carbon pricing deal (MOU backgrounder).
- Implementation agreement (15 May 2026): set carbon pricing and methane commitments and contemplated a pipeline proposal to the Major Projects Office by 1 July 2026 and a national interest designation by 1 October 2026 (release).
- Listing (1 October 2026): the West Coast Oil Pipeline, now called Pacific Link, was added to Schedule 1 of the Building Canada Act. The government said the Major Projects Office, supported by the CER, would aim to finalize conditions by 1 September 2027, with the conditions document serving as the CER certificate, and that Indigenous communities would be offered at least a 10% ownership interest (release).
For Pacific Link, the Building Canada Act replaces the s. 183–186 decision on whether to approve with a deemed-favourable listing, but the CER's technical role continues: the Minister must consult the CER Commission on conditions and cannot issue the document without its confirmation that it will not compromise the safety or security of persons or regulated facilities. Provincial permits in British Columbia and Alberta are still required. Our note on national interest projects covers the listing process in detail.
Practical steps for proponents and investors
- Choose the approval route early: CER certificate, s. 214 order, or national interest listing.
- Prepare a complete application, so that the 450-day clock starts promptly.
- Build Indigenous engagement, participation and equity offers into the project plan from the start; see our note on Indigenous equity and loan guarantees.
- Secure shipper commitments and a defensible toll design before the hearing.
- Plan abandonment funding and liability resources in the financing model.
- Prepare for judicial review within short limitation periods.
Illustration: a midstream company plans a 300 km natural gas pipeline from northeastern British Columbia into Alberta. Because it crosses a provincial border, it is federally regulated and needs a certificate. The company files a complete application in March; the Lead Commissioner sets a 400-day time limit; the Commission recommends approval with 40 conditions; and Cabinet directs issuance within 90 days. A First Nation applies for leave for judicial review within 15 days of the Gazette publication, so the company's lenders make expiry of the review period, or dismissal of the application, a condition of the main construction draw.
How TRW & Co helps
We advise pipeline proponents, shippers, investors, lenders and Indigenous partners on pipeline approvals in Canada. We assess approval routes, review applications and conditions, structure transportation service agreements and toll arrangements, and advise on acquisitions of regulated pipeline assets and Indigenous equity participation. Where hearings or judicial review require it, we work with Canadian-licensed regulatory and litigation counsel. This work connects with our oil, gas and LNG and energy regulatory practices. To discuss a project, contact us.
Frequently asked questions
Who approves interprovincial pipelines in Canada?
The Canada Energy Regulator. For major pipelines, the CER Commission reports with a recommendation and conditions, and the Governor in Council directs the Commission to issue or refuse a certificate. Pipelines of 40 km or less and certain facilities can be approved by Commission order under s. 214. Listed national interest projects follow the Building Canada Act.
How long do CER pipeline approvals take?
The Commission's report must be submitted within the time limit set by the Lead Commissioner, no more than 450 days after a complete application, subject to excluded periods and extensions. The Governor in Council then has 90 days, which can also be extended. Preparation and completeness review add time before the clock starts.
Do pipelines still need a federal impact assessment?
Not under the Impact Assessment Act since 3 September 2026, when SOR/2026-185 removed international and interprovincial pipelines from the Project List. The CER assesses environmental, social, Indigenous and climate factors under s. 183(2) of the CER Act instead.
Can CER pipeline approvals be challenged?
Yes. Judicial review of a Governor in Council order under s. 186 lies to the Federal Court of Appeal with leave, and the application must be filed within 15 days after the order is published in the Canada Gazette. Inadequate Indigenous consultation has been a key ground in past challenges.
Sources
- Canadian Energy Regulator Act, S.C. 2019, c. 28, s. 10 (Justice Laws)
- SOR/2026-185: Regulations Amending the Physical Activities Regulations, Canada Gazette Part II
- Canada–Alberta Memorandum of Understanding backgrounder (27 November 2025)
- Canada and Alberta implementation agreement release (15 May 2026)
- Prime Minister of Canada: West Coast Oil Pipeline listed as Pacific Link (1 October 2026)
General information only, not legal advice. References to statutes, courts and authorities describe published law and practice at the date shown.