Data Centre Leases and Development Agreements

Data centre leases allocate scarce electrical capacity as much as space. With Ontario regulating data centre grid connections, Alberta rationing large-load capacity and Quebec requiring ministerial authorization for large new loads, power terms now decide deals. This note covers structures, power and grid risk, service levels, casualty, expansion rights and approvals.

Rows of server racks in a Canadian facility governed by data centre leases with contracted power

Key takeaways

  • Contracted power and its delivery date, not floor area, drive value in data centre leases.
  • Ontario's s. 28.1 Electricity Act, 1998 conditions connection of data centres on regulatory requirements since 11 December 2025.
  • AESO set an interim 1,200 MW limit for large loads in June 2025.
  • In Quebec, supply of 5 MW or more requires the Minister's authorization under s. 76 of the Régie de l'énergie Act.
  • Casualty clauses should measure restoration by contracted capacity, not by reinstatement of the shell.

What makes data centre leases different

Data centre leases are power contracts dressed as real estate. A tenant leasing a powered shell or a wholesale hall is buying access to a defined amount of critical electrical load, cooling capacity and connectivity, delivered with very high reliability, for 10 to 20 years. The premises matter, but the economics and the risk turn on megawatts. In Canada that risk has sharpened: Ontario now regulates data centre grid connections under s. 28.1 of the Electricity Act, 1998, Alberta's system operator has rationed large-load capacity, and Quebec requires ministerial authorization before Hydro-Québec supplies large new loads.

Rows of server racks in a Canadian facility governed by data centre leases with contracted power
In data centre leases, contracted power and its delivery date drive value more than floor area.

This note sets out the structures used to lease and develop data centres in Canada, the provisions that allocate power and grid connection risk, service levels and remedies, insurance and casualty, expansion rights, and the zoning and environmental approvals that sit underneath. It is written for landlords, developers, hyperscale and colocation tenants, and the investors and lenders that finance them. It is general information rather than advice on a specific transaction.

Structures for data centre leases and development

StructureWhat the tenant getsMain risk allocation
Powered land or powered shell leaseSite or building with committed utility capacity; tenant fits outLandlord delivers power to the site; tenant builds and operates mechanical and electrical systems
Wholesale (turnkey) leaseFitted halls with defined critical IT load, cooling and redundancyLandlord designs, builds and operates infrastructure to service levels
Build-to-suit with development agreementPurpose-built campus delivered in phasesDevelopment agreement governs design, schedule and delivery; lease starts on delivery of each phase
Retail colocation agreementCabinets or cages, power per rack, cross-connectsServices contract rather than a lease; operator controls the facility
Ground lease or joint ventureLong-term land rights or shared ownershipAllocation of capital, power procurement and exit rights among owners

The labels matter in law. A colocation agreement that grants no exclusive possession may not be a lease at all, which affects remedies, registration on title, land transfer tax and treatment in insolvency. A build-to-suit transaction usually pairs a development agreement with an agreement to lease, so that delay and cost risk during construction are handled separately from operating-period obligations.

Power allocation and grid connection risk

For most data centre leases, power is the critical path. Utility connection studies, transmission upgrades and substation equipment can take years, and connection capacity is now subject to explicit regulatory control in several provinces.

Ontario

Section 28.1 of the Electricity Act, 1998, added by S.O. 2025, c. 22 and in force since 11 December 2025, prohibits transmitters and distributors from connecting a "specified load facility" — which includes a data centre meeting regulatory criteria, or another facility whose demand exceeds a prescribed amount — unless they are satisfied that the "specified connection requirements" set by regulation are met. Those requirements may include approvals and criteria on economic development and job creation. The section does not apply where a connection request was submitted before 3 June 2025.

In ERO notice 025-1001 (September 2025), the province proposed requiring the Minister's approval for covered data centres, floating "greater than 50 megawatts" as a possible threshold; parties should check whether final regulations have been made before relying on any threshold.

Alberta

The Alberta Electric System Operator announced in June 2025 an interim limit of 1,200 MW for large-load projects such as data centres, pending a new large-load framework (AESO fact sheet, 4 June 2025). Projects seeking capacity beyond the interim allocation have explored on-site or adjacent self-generation, often gas-fired, which brings its own permitting and emissions questions.

Quebec

Under s. 76 of the Act respecting the Régie de l'énergie, a distributor holding exclusive rights must seek the Minister's authorization to supply any request of at least 5 MW (or 50 kW for cryptocurrency mining). Data centre projects in Quebec therefore depend on a government decision on supply, not only on a utility study.

How the lease should deal with it

  • Define contracted capacity precisely: critical IT load in kW or MW, power usage effectiveness assumptions, redundancy level and the point of delivery.
  • Tie rent commencement and phased delivery to energization milestones, with outside dates and remedies (rent abatement, liquidated damages, termination) if power is late.
  • Allocate the cost of connection studies, utility deposits and network upgrades, and say who bears the risk that an approval is refused or conditioned.
  • Address curtailment and demand-response obligations, and whether interruptions imposed by the utility or system operator count against service levels.
  • Deal with electricity procurement: pass-through of utility tariffs, retail contracts or corporate power purchase agreements, and allocation of clean-energy attributes.

Development agreements for build-to-suit campuses

Where a tenant commits before the facility exists, the development agreement does much of the work that data centre leases cannot. It should fix the basis of design — critical load per hall, redundancy topology (for example N+1 or 2N), cooling technology, rack densities and any liquid-cooling readiness for high-density AI workloads — and a change process for tenant-driven design changes, with cost and schedule consequences agreed in advance.

The key commercial terms are the delivery schedule for each phase, the conditions to delivery (energization, commissioning tests witnessed by the tenant, occupancy permits), and the consequences of delay. Tenants usually ask for a delay credit regime and a long-stop date after which they may walk away from an undelivered phase, sometimes with reimbursement of their own fit-out or equipment costs. Developers seek relief for utility, regulatory and force majeure delay and a cap on liability, and will want the tenant's obligations to be strong enough to support construction financing.

Other points that repay attention include: tenant step-in or completion rights if the developer defaults, which lenders will need to approve; ownership of long-lead equipment the tenant pre-orders; confidentiality of the tenant's identity and design information; and allocation of construction lien and holdback risk under provincial construction statutes. On a phased campus, the agreement should also say how far the tenant's commitment to later phases is firm or optional.

Operations, security and sustainability terms

Operational provisions deserve the same attention as the economics. Tenants need 24-hour access, escorted access rules for contractors, rights to install their own security systems inside their space, and control over maintenance windows that could affect their equipment. Landlords need rules on hazardous materials (batteries, refrigerants, fuel), on loading and floor capacity, and on changes to the tenant's power draw. Both sides should agree how data protection and confidentiality obligations apply to landlord staff who may have physical access to equipment holding personal information or sensitive data.

Sustainability is increasingly a lease issue. Tenants with public climate targets ask for renewable electricity sourcing, reporting of energy and water use, and allocation of renewable energy certificates. Some municipalities and developers are exploring the reuse of waste heat in district energy systems, which requires agreements on metering, interruption and liability. Green lease clauses should be realistic about what the landlord controls and should not promise outcomes that depend on the utility or the grid mix.

Service levels and remedies

Wholesale and colocation data centre leases include service level agreements for power availability, temperature and humidity ranges, and physical security. The negotiation points are the definition of an outage (at the rack, the hall or the building), measurement and reporting, exclusions (scheduled maintenance, tenant-caused events, utility failure where backup performs), the credit schedule, and the point at which chronic failure gives the tenant a termination right. Landlords seek to make credits the sole remedy; tenants with mission-critical workloads push for termination rights and for step-in rights to cure failures of critical plant.

Practical point

Align the service levels in the lease with the landlord's maintenance and operations contracts and with the equipment warranties. A landlord that promises 100% power availability to a tenant but has only commercially reasonable obligations from its operator and utility carries an unhedged gap.

Insurance, casualty and expansion rights

Standard office or industrial casualty clauses do not fit. A fire in an electrical room may leave the shell intact but make the premises unusable for months while long-lead switchgear and generators are replaced. Data centre leases should measure restoration by time to restore contracted capacity, not floor area, and give tenants termination rights if restoration will exceed a set period. Insurance provisions should cover property and equipment breakdown insurance on landlord infrastructure, the tenant's own equipment (often high-value servers and GPUs), business interruption, cyber and liability, with clear mutual waivers of subrogation.

Expansion rights are often as valuable as the initial term. Hyperscale tenants seek rights of first offer or first refusal over adjacent halls, buildings or land, reservations of future power capacity, and options with pre-agreed pricing. Landlords and their lenders need these rights to be time-limited and clearly subordinate to financing, and need to consider their effect on the value of unbuilt phases. Our notes on rights of first refusal and lease assignment and change of control cover related clauses.

Zoning and environmental approvals

Data centres are usually permitted in industrial zones, but municipalities increasingly scrutinize them for noise from cooling equipment and generators, water use for evaporative cooling, building height for multi-storey facilities, and the limited employment they generate compared with other industrial uses. Development schedules should allow for site plan approval, minor variances or rezonings, and community consultation where needed.

Environmental approvals typically include air permits for standby diesel or gas generators, which in Ontario generally require an environmental compliance approval or registration under the Environmental Protection Act, together with water-taking permits where cooling draws on ground or surface water, and stormwater approvals. Facilities with on-site gas-fired generation may also fall into provincial or federal carbon pricing systems. Sites on former industrial land need environmental due diligence and, in Ontario, may need a record of site condition before a more sensitive use; see our note on brownfield redevelopment.

Investment and financing considerations for data centre leases

Investors and lenders value data centre leases on tenant credit, term, contracted power and the reliability of the delivery chain. Due diligence should confirm the status of connection agreements and regulatory approvals, the landlord's rights to power capacity, and whether tenant rights of termination for late delivery or chronic outages could undermine cash flow. Foreign acquirers should also consider whether a data centre platform raises national security questions under the Investment Canada Act, particularly where it hosts government or sensitive data.

Illustration: a developer signs a 15-year lease with a cloud tenant for a 36 MW campus delivered in three 12 MW phases. Rent on each phase starts on energization of that phase. If phase two is energized more than 180 days after its target date because of a utility upgrade delay, rent is abated day-for-day and, after a further period, the tenant may terminate that phase. The developer back-stops this exposure by negotiating milestones with the utility and building contingency into its financing.

How TRW & Co helps

We advise developers, landlords, operators, tenants and investors on data centre leases and development agreements in Canada. We structure powered shell, wholesale and build-to-suit transactions, negotiate power delivery, service level, casualty and expansion provisions, and review grid connection, procurement and approval risk with technical advisers. On acquisitions and financings we lead legal due diligence and coordinate foreign investment and competition analysis. This work connects with our commercial real estate, power and renewables and technology and AI practices, and with our note on data centre grid connections. To discuss a project, contact us.

Frequently asked questions

Does Ontario regulate data centre grid connections?

Yes. Section 28.1 of the Electricity Act, 1998, in force since 11 December 2025, bars transmitters and distributors from connecting a specified load facility, including qualifying data centres, unless regulatory connection requirements are met. It does not apply to connection requests made before 3 June 2025. The details depend on regulations, which were proposed in ERO notice 025-1001.

What is the difference between a wholesale data centre lease and colocation?

A wholesale lease grants exclusive possession of halls or buildings with a defined critical IT load, usually for a long term. Retail colocation is a services agreement for cabinets or cages in an operator-controlled facility. The difference affects remedies, registration, land transfer tax and treatment in insolvency.

Who bears the risk of late power delivery?

It depends on negotiation. Tenants usually tie rent commencement to energization and seek abatement, liquidated damages and termination rights for prolonged delay. Landlords try to exclude delays caused by utilities or regulators, or cap their exposure. The lease should also allocate the cost of connection studies and network upgrades.

Can a data centre in Quebec simply request power from Hydro-Québec?

Not for large loads. Under s. 76 of the Act respecting the Régie de l'énergie, a distributor with exclusive rights must seek ministerial authorization to supply a request of at least 5 MW, or 50 kW for cryptocurrency mining. Projects should plan for that authorization in their timetable.

Sources

  1. Electricity Act, 1998, S.O. 1998, c. 15, Sched. A, s. 28.1 (Ontario e-Laws)
  2. ERO 025-1001: New requirements for data centres seeking to connect to the electricity grid in Ontario
  3. AESO: Large Load Integration Fact Sheet (June 2025)
  4. Act respecting the Régie de l'énergie, CQLR c. R-6.01 (LégisQuébec)

General information only, not legal advice. References to statutes, courts and authorities describe published law and practice at the date shown.